Question 1403: To ask the Minister for the Environment, Heritage and Local Government if a local authority has made an application to his Department in relation to the provision of a water supply in an area (details supplied); and if he will make a statement on the matter. [2370/08]

Photo of John GormleyJohn Gormley (Dublin South East, Green Party)
Link to this: Individually | In context

I understand that works recently carried out under Contract 3B (Trunk Watermains from Ardscull to Athy) of Phase 1 of the Kildare Water Supply Scheme, which is being funded under my Department's Water Services Investment Programme 2007-2009, will provide interim water supply facilities for the Ballyroe area. A longer-term solution will be provided by another element of Phase 1 of the Kildare Water Supply Scheme — the River Barrow Abstraction Scheme and Associated Pipelines. This project is also included in the Investment Programme as a scheme to begin construction in 2008.

Comments

No comments

Log in or join to post a public comment.