Written answers
Wednesday, 19 December 2007
Department of Communications, Energy and Natural Resources
Alternative Energy Projects
3:00 pm
Jan O'Sullivan (Limerick East, Labour)
Link to this: Individually | In context
Question 91: To ask the Minister for Communications, Energy and Natural Resources the way he will manage and proceed with the investment required in order for the national grid to allow for more renewable energy; when he expects the 3000 MW of renewable energy in the grid connection application process to be completed; and if he will make a statement on the matter. [35608/07]
Eamon Ryan (Dublin South, Green Party)
Link to this: Individually | In context
The Investment Programme of at least €770 million by EirGrid in the transmission grid up to 2013 is designed to meet overall electricity demand, enhance security of supply and accommodate the connection of renewable energy sources to the grid in line with our ambitious targets up to 2020.
Decisions in relation to further investment in the grid will be informed by the findings of the All–Island Grid study, which will be published early in 2008. EirGrid is also preparing a Grid Development Strategy 2008–2025. The Strategy will take account of growing transmission demands, grid technology development and the growth of renewable energy as well as spatial strategy and regional development objectives.
There are now more than 1,000 Megawatts of renewable energy connected to the grid. EirGrid is currently completing a connections offer programme to the 1300 megawatts of renewable energy under "Gate 2". In excess of 3,000 megawatts of renewable energy applications is being assessed under the new "Gate 3" round.
No comments