Written answers

Tuesday, 20 November 2007

Department of Education and Science

Schools Building Projects

8:00 pm

Photo of Mary O'RourkeMary O'Rourke (Longford-Westmeath, Fianna Fail)
Link to this: Individually | In context

Question 432: To ask the Minister for Education and Science the situation regarding the provision of new school facilities for a primary school (details supplied) in County Longford. [29512/07]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

I can confirm to the Deputy that the Department is in receipt of an application for large scale capital funding from the school to which she refers. The project has been assessed in accordance with the published prioritisation criteria for large scale building projects. Progress on the proposed works is being considered in the context of the multi-annual School Building and Modernisation programme.

Photo of Mary O'RourkeMary O'Rourke (Longford-Westmeath, Fianna Fail)
Link to this: Individually | In context

Question 433: To ask the Minister for Education and Science the developments that have taken place with regard to the provision of a new second level school in Kilbeggan, County Westmeath. [29513/07]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

As the Deputy will probably be aware, under the N4/M4 Area Development Plan published by the Commission on School Accommodation, it is recommended that the school to which she refers be re-located to a greenfield site.

The Department is in the process of progressing the issue of the transfer of a site to enable this development.

Thereafter, progress on the building project itself will be considered in the context of the multi-annual School Building and Modernisation Programme.

Photo of Mary O'RourkeMary O'Rourke (Longford-Westmeath, Fianna Fail)
Link to this: Individually | In context

Question 434: To ask the Minister for Education and Science the developments that have taken place with regard to the provision of a new second level school in Kinnegad, County Westmeath. [29514/07]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

As the Deputy will probably be aware, under the Area Development Plan for the N4/M4 corridor published by the Commission on School accommodation, provision of a new post primary school for Kinnegad post 2011 is recommended.

Westmeath County Council has been made aware of this requirement for the purposes of reserving a site to enable this development.

Thereafter, progress on the building project itself will be considered in the context of the multi-annual School Building and Modernisation Programme.

Photo of Mary O'RourkeMary O'Rourke (Longford-Westmeath, Fianna Fail)
Link to this: Individually | In context

Question 435: To ask the Minister for Education and Science the situation regarding provision of a new primary school (details supplied) in County Westmeath. [29515/07]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

I can confirm to the Deputy that the Department is in receipt of an application for large scale capital funding from the school to which she refers. The project has been assessed in accordance with the published prioritisation criteria for large scale building projects. Progress on the proposed works is being considered in the context of the multi-annual School Building and Modernisation programme.