Written answers

Thursday, 26 April 2007

Department of Education and Science

Schools Building Projects

5:00 pm

Photo of John DeasyJohn Deasy (Waterford, Fine Gael)
Link to this: Individually | In context

Question 200: To ask the Minister for Education and Science the cost of providing prefabricated buildings for the past ten years at a school (details supplied) in County Waterford; and the cost per year. [15767/07]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

The total amount spent on temporary accommodation from 1999 to the end of 2006 is €551,303. The breakdown of costs per year is outlined in the following table.

There is currently a permanent School Building project at an early stage of architectural planning at the school referred to by the Deputy. My Department has recently received a revised Stage 1/2 submission which is currently being examined. If the revised submission is approved, the project will be authorised to progress to the next stage of architectural planning.

Progression of the project to tender and construction will be considered in the context of the Department's multi-annual School Building and Modernisation Programme.

Holy Cross NS, Waterford
YearAmount
1999 12,023.10
2000 29,373.09
2001 56,053.10
2002 76,246.06
2003 70,499.72
2004 65,057.24
2005101,854.04
2006140,196.75
Total551,303.10

Comments

No comments

Log in or join to post a public comment.