John Browne (Wexford, Fianna Fail)
Link to this: Individually | In context
Details of amounts allocated and drawn down on a project basis for each of the years from 1997 to 2006 under the Department's Coastal Protection Programmes are set out in the following tables. In addition, each local authority contributed 25% of the cost of the projects in their areas. In 2005 and 2006 this Department co-funded with the Department of Community, Rural and Gaeltacht Affairs (37.5% each Department) coast protection projects in CLÁR areas under the Coastal Development Measure. These are identified in the following tables.
1997 Coast Protection Programme |
County | Location | Project | 1997 Allocation | 1997 |
| | | € | € |
Wexford | Rosslare Strand | Aerial survey/ mapping of coastline | 24,752.27 | 24,752.27 |
| Courtown | Rock revetment | 52,326.46 | 53,326.46 |
| Rosslare | Maintenance | 85,000 | 84,969.60 |
Waterford | Tramore | Strengthening of clay cliffs, sand dunes, improvement works to main promenade | 142,845.53 | 141,649.44 |
Wicklow | Murrough | Rock armour revetment | 142,845.53 | 45,193.79 |
| Bray | Beach nourishment/ groyne protection | 52.969.66 | 52,969.66 |
Sligo | Enniscrone | Planting of grass | 6,012.21 | 6,012.21 |
| Strandhill | Wind fencing | 38,092.14 | 38,092.14 |
Louth | Annagassan | Rock revetment | 12,501.84 | 12,501.84 |
Donegal | Inver | Completion of sea wall | 12,697.38 | 12,697.38 |
| Rye/ Rathmullen | Seawall protection | 49,519.79 | 49,519.79 |
| Teelin | Seawall protection | 76,184.26 | 76,184.26 |
Meath | Laytown | Study | 19,046.07 | 19,040.99 |
Mayo | Bertra | Dune protection | 52,376.70 | 52,376.70 |
| Claggan | Dune protection | 14.284.55 | 14,284.55 |
Dublin | Burrow | Study | 19,790.14 | 19,790.14 |
Cork | Glandore | Seawall protection | 154,922 | 154,922.01 |
Clare | Rinvella | | 126,973.81 | 126,973.81 |
GENERAL | | | | |
| CZM | Study | 0 | 57.14 |
| Sensitivity Study | | 19,571.74 | 19,571.74 |
| ECOPRO manual | | 1,537.65 | 1,537.65 |
1998 Coast Protection Programme |
County | Location | Project | 1998 Allocation | 1998 |
| | | € | € |
Dublin | Burrow | Study | 6,840 | 6,840 |
Louth | Annagassan | Study | 179,038.15 | 179,038.15 |
Wexford | Rosslare | Aerial survey/ mapping of coastline | 9,803.65 | 9,803.65 |
| Rosslare | Maintenance | 59,215.51 | 59,215.51 |
Wicklow | Bray | Breakwater and groyne | 940,214 | 940,214 |
| Murrough | Rock armour | 3,405.44 | 3,405.44 |
1999 Coast Protection Programme |
County | Location | Project | 1999 Allocation | 1999 |
| | | € | € |
Louth | Annagassan | Detailed design of Phase 2 protection scheme | 19,046.07 | 19,046.07 |
Fingal | Portrane | Dune protection | 19,046.07 | 0 |
| Portrane | Study | 9,523 | 0 |
Dún Laoghaire/Rathdown | Vico Road | Protection works at Vico Road (Design) | 266,645 | 13,343.49 |
Wicklow | Bray-Coast Prot. | Phase 1 | 775,175 | 489,057 |
| Bray | Harbour Wall | 952,304 | 298,306 |
Wexford | Courtown | Dune protection | 57,138 | 67,614 |
| Curracloe | Study for coast management | 38,092 | 28,569.11 |
| Ballyconnigar | Cliff protection | 95,230.36 | 95,230.36 |
| Rosslare Strand | Beach protection | 128,561 | 0 |
| Wave Buoys Maintenance | Maintenance | 9,523.04 | 11,963.47 |
| Rosslare | Beach protection work | 14,284.55 | 23,067.08 |
| Rosetown | Cliff protection (Design) | 95,230.36 | 4,791.57 |
| Cullenstown | Detailed design for protection works | 28,569.11 | 21,902.98 |
| Rosslare | New scheme | 0 | 5,534.79 |
Cork | Youghal | Further study of protection options | 38,092.14 | 26,664.50 |
| Roscarberrry Owennahincha | Road protection | 42,853.66 | 42,853.66 |
| Barley Cove | Study of required dune protection works | 19,046.07 | 19,046.07 |
| Roscarberry Warren | Groyne | 109,514.91 | 16,452 |
Kerry | Waterville | Protection works | 152,368.57 | 152,368.57 |
| Baile an Rannaigh | | 19,046.07 | 0 |
Clare | Quilty | Protection works | 952,303.56 | 771,987.74 |
Galway | Inishboffin Isl. | Road protection | 95,230.36 | 98,820.54 |
| Aughinish Isl. | Causeway protection | 38,092.14 | 38,092.14 |
| Roundstone/ Gorteen | Dune re-instatement | 19,046.07 | 20,783.07 |
| Tawin Isl. | | 42,853.66 | 0 |
| Mweelon/Ballynacloghy | | 82,136.82 | 109,514.91 |
Mayo | Claggan Isl. | Dune reinstatement | 28,569.11 | 27,503.62 |
| Belmullet/Elly Bay | Study | 19,046.07 | 22,022.97 |
Sligo | Mullaghmore | Road protection | 114,276.43 | 22,761.33 |
| Strandhill | Study | 33,330.63 | 34,568.62 |
Donegal | Bundoran | Road protection | 190,460.71 | 114,276.43 |
| Mountcharles | Coast protection | 82,850.41 | 82,850.41 |
| Inver | Coast protection | 80,945.80 | 57,138.21 |
Waterford | Tramore | Coast protection | 32,222.33 | 32,222.33 |
GENERAL | | | | |
Louth | Coastal survey | | 50,789.52 | 66,706.96 |
Waterford | Coastal survey | | 76,184.29 | 0 |
East Coast | Aerial survey | | 101,579.05 | 51,909.43 |
GIS | Initial setup | | 33,013.19 | 40,074.38 |
Marine Institute | Coastal viewer system | | 12,697.38 | 12,697.38 |
2000 Coast Protection Programme |
County | Location | Project | 2000 Allocation | 2000 |
| | | € | € |
Louth | Annagassan | Phase 2 Protection Scheme | 285,691.00 | 88,724.59 |
| Coastal Survey | | 2,500 | 2,343.03 |
Fingal | Portrane | | 176,176 | 0 |
Dún Laoghaire/ Rathdown | Vico Road/Killiney | Cliff Protection works | 571,382 | 38,124.72 |
Dublin Corporation | Bull Island causeway | Study of effects of breaching causeway | 142,846 | 41,943.26 |
Wicklow | Bray | Phase 1 | 476,152 | 94,734.31 |
| | Harbour wall Phase 3 | 190,460 | 355,322.67 |
| | Phase 2 Beach nourishment | 2,095,068 | 1,555,026.45 |
Wexford | Courttown | | 95,230 | 0 |
| Rosslare strand N end Spit | Beach Protection | 238,076 | 56,756.48 |
| Cullenstown | Revetment works and training walls | 476,152 | 109,229.22 |
| Rosslare | Maintenance | 20,500 | 19,656.33 |
Waterford | Tramore | Promenade wall strengthening | 442,821 | 46,119.29 |
| Cunnigar | Design of protection works | 33,331 | 13,894.35 |
| Cunnigar | | 0 | 12,656.36 |
Kerry | Rossbeigh | Consultancy study | 38,092 | 38,092.14 |
| Waterville | Upgrade and road protection | 76,184 | 80,568.08 |
| R561 Dingle to Castlemaine | Rock armour | 1,396,712 | 1,396,711.89 |
Clare | Quilty | Protection scheme | 185,699 | 202,163.57 |
| Seafield | Dune protection works | 19,046 | 20,474.53 |
| Ballyvaughan | Road protection works | 152,369 | 116,734.32 |
Galway | Aughinish Island | Causeway protection works | 57,138 | 58,566.67 |
| Cleggan | Beach road protection | 95,230 | 98,620.30 |
| Tawin Island | Beach road protection | 38,092 | 49,519.79 |
| Gorteen Beach | Beach protection | 47,615 | 48,567.48 |
| Renville | Coast protection to public recreation area | 42,854 | 50,282.58 |
| Clifden Beach | Coast protection to public recreation area | 95,230 | 95,706.51 |
| Inishbofin | | 95,230 | 0 |
| Inishmore Island | Beach road | 95,230 | 57,138.21 |
Galway | Oranmore/ Mweelon | Road protection works | 53,329 | 39,520.60 |
| Oranmore/ Mweelon 1999 | | 0 | 20,066.94 |
Mayo | Westport/Bertra | | 19,046 | 0 |
| Achill | Dune protection works | 28,569 | 31,838.36 |
| Elly Bay | Seawall repairs/dune protection | 123,799 | 102,108.93 |
| Bertra Beach | Dune protection works | 28,569 | 47,799.92 |
| Fahy-Ballycroy | Sea outfall renewal and coast protection | 57,138 | 59,142 |
| Bundoola Belmullet | Repairs to sea wall | 95,230 | 20,144.08 |
| Carrowmore Beach | | 28,569 | 0 |
| Keel Beach | Dune protection works | 14,284 | 18,114.72 |
| Mulranny Causeway | | 85,707 | 0 |
Sligo | Strandhill | Dune protection works | 19,046 | 17,427.16 |
| Mullaghmore | Road protection works | 141,893 | 112,989.28 |
| Strandhill | Dune protection works | 104,753 | 0 |
| Pollacheeney | Protection works | 71,423 | 68,565.86 |
Donegal | Bundoran | Road/Cliff protection | 266,644 | 296,173.07 |
| Kerrykeel | Repairs to sea wall | 71,423 | 61,628.32 |
| Mountcharles | Rock armour | 95,230 | 101,098.01 |
| Rye, Rathmullen | Sea wall rock armouring | 119,038 | 144,427.31 |
| Inver | Coast protection | 23,807 | 25,743.62 |
GENERAL | East Coast | | 88,8882 | 0 |
| Coastal Surveys | | 126,974 | 45,705.48 |
| GIS System | | 25,395 | 224.91 |
| GIS Maintenance | | 0 | 16,811.33 |
| Wave Buoy | | 25,395 | 17,300.35 |
| Pilot Project | for project dissemination | 12,697 | 3,802.55 |
| Research Startup | | 25,395 | 5,743.77 |
2001 Coast Protection Programme |
County | Location | Project | 2001 Allocation | 2001 |
| | | € | € |
Sligo | Strandhill | Slipway | 133,322.50 | 14,284.55 |
Sligo | Strandhill | Shoreline Protection | 485,674.81 | 69,994.31 |
Sligo | Mullaghmore | Road Protection Works +add fund | 423,775.08 | 385,546.76 |
Sligo | Pollacheeny | Study & Detailed Design | 30,473.71 | 29,616.64 |
Donegal | Drung, Quigley's Point | Rock Armour Work | 190,460.71 | 207,652.65 |
Donegal | Keadue, Kincasslagh | Seawall | 238,075.89 | 31,746.80 |
Donegal | Mountcharles | Road protection works | 285,691.07 | 233,435.54 |
Donegal | Mahery, Dungloe | Road protection works | 95,230.36 | 23,662.38 |
Donegal | Kerrykiel, Rossakill | Road protection works | 119,037.94 | 118,048.50 |
Donegal | Kerrykeel | Sea wall repairs | 0 | 1,645.58 |
Donegal | Inver | Concrete slab & Low level wall | 23,807.59 | 36,186.58 |
Donegal | Carrickaroary | Repointing existing sea wall | 16,189.16 | 3,176.88 |
Donegal | Lagg, Malin Head | Study of coastal processes in the area | 19,046.07 | 0.00 |
Donegal | Bundoran | Shoreline protection (UDC) | 0 | 87,528.52 |
Donegal | Rye Rathmullan | Sea Wall | 0 | 5,482.41 |
Galway | Auginish Island | Causeway Protection Works | 38,092.14 | 38,092.14 |
Galway | Inishboffin | Protection Works to | 95,230.36 | 95,230.36 |
Galway | | South Facing Shore | | |
Galway | Inishboffin | Erosion Study of South/facing shore | 38,092.14 | 28,355.82 |
Galway | Inishboffin | Road Protection Works | 47,615.18 | 0.00 |
Galway | Renvyle | Road Protection at Ard na Greevagh | 46,980.31 | 47,615.18 |
Galway | Rusheenduff Renvyle | Coastal Protection | 104,753.39 | 0.00 |
Galway | Sailin to Silver Strand | Protection Works | 142,845.53 | 0.00 |
Galway | Inishmore | Airstrip Protection | 7,618.43 | 8,281.87 |
Galway | Ballyconnelly | Road Protection Works | 85,707.32 | 85,707.32 |
Galway | Cleggan | | 0 | 59.73 |
Galway | Roundstone Pier | Study | 31,743.45 | 18,411.20 |
Mayo | Westport / Bertra | Dune Protection | 28,569.11 | 28,569.11 |
Mayo | Carrowmore Beach | Dune Protection | 19,046.07 | 19,046.07 |
Mayo | Roonagh, Louisburg | Road Protection Works | 28,569.11 | 28,569.11 |
Mayo | Belmullet Town | Repair Seawalls | 95,230.36 | 95,230.36 |
Mayo | Mulranny Causeway | Repairs to side/surface of causeway/repair stones | 85,707.32 | 85,707.32 |
Mayo | Bundoola Belmullet | Repairs to seawall | 75,085.96 | 75,085.96 |
Mayo | Claggan Island | Dune protection work | 50,024.51 | 53,759.02 |
Mayo | Elly Bay | Seawall Repairs & Dune Protection | 133,322.50 | 76,673.57 |
Mayo | Bunnafolly | Protection works | 19,046.07 | 0.00 |
Louth | Annagassan | Phase 2 Protection Works | 190,460.71 | 149,908.10 |
Louth | Salterstown | Protection works | 38,092.14 | 33,454.68 |
Waterford | Ballyvoile | Study of Road Protection Works | 33,330.62 | 31,484.01 |
Waterford | Tramore | Promenade Wall Strengthening | 904,688.38 | 880,041.04 |
| Tramore | Additional funding for Prom. wall | 155,165.48 | 0.00 |
Wexford | Courtown | Detailed Design of offshore breakwater protection scheme | 190,460.71 | 0.00 |
Wexford | Courtown | Revetment Works+ add funding | 95,230.36 | 86,899.68 |
Wexford | Cullenstown | Revetment Works & training walls | 557,097.58 | 685,612.85 |
Wexford | Rosslare Strand | Study of Nth end of Spit | 76,184.28 | 51,999.57 |
Wexford | Rosslare Strand | Maintenance | 0.00 | 22,771.86 |
Wexford | Rosslare Strand | Revetment works | 142,845.53 | 71,422.77 |
Wexford | Rosslare Strand | New Scheme | 0 | 188.78 |
Cork | Garretstown | Road Protection Works | 190,460.71 | 0.00 |
Cork | Durrus to Ahakista | Road protection works | 190,460.71 | 66,314.61 |
Cork | Youghal | Preparation of tender and planning documents | 19,046.07 | 19,046.07 |
Cork | Youghal | Sea wall repairs | 28,569.11 | 28,569.11 |
Kerry | R561 Dingle to Castlemain Rd | Revetment Works | 634,869.04 | 1,386,430.06 |
Clare | Quilty | Protection Scheme | 47,615.18 | 73,815.11 |
Clare | Clahanes, Liscannor | Concrete Wall | 142,845.53 | 175,086.91 |
Clare | Rinvalla Bay | Road protection works | 190,460.71 | 240,929.66 |
Clare | Aughinish Island | Causeway protection works | 47,615.18 | 39,276.27 |
Wicklow | Bray | Phase 2 Coast Protection | 285,691.07 | 647,673.60 |
Wicklow | Bray | Pier Remedial Works, Ext of harbour wall works | 1,097,053.70 | 792,131.26 |
Wicklow | Bray | Coast Protection Scheme | 0 | 20.02 |
Dublin | Bull Island | Study | 100,902.28 | 63,880.52 |
Dún Laoghaire / Rathdown | Vico Road | Cliff Protection Works | 666,612.49 | 0.00 |
GENERAL | | | | |
| East Coast | Aerial Survey-Carnsore to Killiney | 63,281.12 | 63,281.12 |
| Coastal Surveys | General Coastal & Project Related | 10,240.44 | 10,240.44 |
| GIS System | Customisation, Maintenance & Training | 2,384.52 | 2,384.52 |
| GIS System 2001 | Customisation, Maintenance & Training | 0 | 33,284.28 |
| Wave Buoys | Maintenance & Deployment | 3,000 | 2,989.61 |
2002 Coast Protection Programme |
County | Location | Project | 2002 Allocation | 2002 |
| | | € | € |
Sligo | Strandhill | Shoreline Protection | 532,500.00 | 532,500.00 |
Sligo | Mullaghmore | Road Protection | 67,500.00 | 67,286.25 |
Donegal | Keadew Kincaslagh | Sea Wall | 157,500.00 | 183,974.90 |
Donegal | Maghery Dungloe | Road Protection | 75,000.00 | 82,330.31 |
Donegal | Mountcharles | Road Protection | 0 | 9,249.64 |
Donegal | Kerrykeel | Road Protection | 0 | 1,180.65 |
Donegal | Carrickaroary | Repointing existing sea wall | 0 | 16,705.54 |
Donegal | Drung, Quigleys Point | Rock Armour | 0 | 11,606.83 |
Donegal | Lagg, Malin Head | Study of coastal processes | 0 | 23,293.18 |
Donegal | Inver | Protection works | 0 | 991.29 |
Galway | Inishboffin | Protection Works to Sth Facing Shore | 142,875.00 | 142,875.00 |
Galway | Salin to Silverstrand | EIS\Study | 78,500.00 | 79,830.46 |
Galway | Tawin Island | Road Protection | 57,150.00 | 53,913.51 |
Mayo | Claggan Island | Repair works | 20,000.00 | 24,869.00 |
Mayo | Bunnafolly | Protection Works | 22,500.00 | 27,108.00 |
Mayo | Lacken | Cliff\Road Study | 22,500.00 | 22,500.00 |
Mayo | Elly Bay | Installation of ECAB Units | 172,500.00 | 148,608.00 |
Louth | Bellurgan | Embankment Reinstatement | 225,000.00 | 170,151.75 |
Louth | Louth Coastline | Survey of Coastline | 9,000.00 | 7,568.25 |
Louth | Whitestown | Rock Armour Protection | 37,500.00 | 37,335.64 |
Louth | Blackrock | Seawall Protection | 22,500.00 | 32,487.75 |
Louth | Salterstown, Cruisetown, Dunany | Repairs & Protection of Road Verge | 390,000.00 | 393,617.25 |
Louth | Seapoint | Dune Protection Works | 75,000.00 | 75,000.00 |
Louth | Blackrock to Dundalk | Study | 37,500.00 | 36,300.00 |
Louth | Shelling Hill/Gyles Quay | Protection works | 11,250.00 | 34,419.00 |
Louth | Carlingford Harbour | Damaged navigation light | 7,500.00 | 623.25 |
Louth | Annagassan Harbour | Protection works | 7,500.00 | 26,068.50 |
Waterford | Tramore | Promenade Refurbishment | 93,750.00 | 228,194.88 |
Waterford | Cunnigar | Rock Revetment | 266,250.00 | 244,273.60 |
Wexford | Rosslare Strand | Study of North End Spit | 147,607.00 | 114,435.00 |
Wexford | Courtown | Detailed design of offshore breakwater | 165,000.00 | 133,810.34 |
Wexford | Rosslare Strand | Revetment Works | 186,187.00 | 77,846.49 |
Wexford | Rosslare Strand | Maintenance | 0.00 | 13,292.00 |
Wexford | Rosslare Strand | Capital | 63,281.25 | 0.00 |
Wexford | Cahore | Rock Groynes & Beach Nourishment | 112,500.00 | 42,966.58 |
Wexford | Ballyconnigar | Rock Revetment | 57,375.00 | 21,750.00 |
Cork | Garrettstown | Road Protection Works | 116,250.00 | 209,259.83 |
Cork | Durrus to Ahakista | Road Protection Works | 132,750.00 | 135,179.00 |
Cork | Warren | Beach Groynes | 123,750.00 | 112,500.00 |
Cork | Youghal | Planning/Contract documents/Foreshore | 37,500.00 | 37,500.00 |
Kerry | Ballyheigue/Inch | Road Protection Works | 375,000.00 | 414,243.46 |
Kerry | Knightstown | Protection Works | 37,500.00 | 37,856.12 |
Clare | Carrigolt | Protection Works to National Monument | 193,000.00 | 45,897.00 |
Wicklow | Bray | Pier Repair works | 423,000.00 | 440,244.00 |
Dublin | Dún Laoghaire/Rathdown | Shanganagh Study | 19,125.00 | 7,482.91 |
Dublin | Dún Laoghaire/Rathdown | Vico Road Revetment | 262,500.00 | 212,718.05 |
Dublin | Portmarnock Dunes | Protection Works | 40,500.00 | 37,487.86 |
GENERAL | | | | |
| Coastal Study | Consultancy Study | 80,000.00 | 2,955.00 |
| Coastal Surveys | General Coastal & Project Related | 20,000.00 | 4,212.00 |
| GIS System | Customisation, Maintenance & Training | 20,000.00 | 9,537.00 |
| Wave Buoys | Maintenance & Develop | 20,000.00 | 7,391.00 |
| Beach Monitoring | Monitoring of nourished Beach, Bray, Co Wicklow | 40,000.00 | 5,816.00 |
| East Coast | Aerial Survey-Carnsore to Killiney | | 21,785.00 |
2003 Coast Protection Programme |
County | Location | Project | 2003 Allocation | 2003 |
| | | € | € |
Mayo | Elly Bay | Installation of ECAB Units | 75,000.00 | 69,182.59 |
Mayo | Devlin Townland | Installation of rock armour, retaining wall | 60,000.00 | 60,000.00 |
Louth | Bellurgan | Embankment Reinstatement | 7,500.00 | 5,736.00 |
Louth | Salterstown | Repairs & protection of Road Verge | 90,000.00 | 90,000.00 |
Louth | Carlingford Harbour | Damaged Navigational Light | 5,250.00 | 2,253.00 |
Louth | Shore Rd Dundalk | Sea Defence Embankment | 56,250.00 | 58,500.00 |
Louth | Blackrock | Rock armour | 41,250.00 | 40,905.00 |
Louth | Annagassan | Protection Works | 7,500.00 | 6,706.50 |
Louth | Cruisetown | Extend coastal protection | 60,000.00 | 60,738.00 |
Louth | Salterstown pier | Protection works | 18,750.00 | 22,527.25 |
Donegal | Drung, Quigleys Pt. | Road Protection Works | 40,000.00 | 40,277.59 |
Donegal | Meenacross | Rebuild portion of wall, repoint wall | 15,000.00 | 15,000.00 |
Donegal | Muckross | Rock armour revetment to protect public road | 60,000.00 | 60,000.00 |
Clare | Carrigaholt Castle | Protection Works to National Monument | 30,000.00 | 32,661.50 |
Clare | Cappagh | Road Protection Works | 75,000.00 | 74,700.00 |
Clare | Carrigaholt | Reconstruction of rock revetment | 22,500.00 | 21,753.00 |
Clare | Doonbeg | Rock armour | 15,000.00 | 17,011.50 |
Clare | Liscannor | Rock armour | 15,000.00 | 13,710.53 |
Wexford | Rosslare Strand | Study | 15,000.00 | 8,616.23 |
Wexford | Rosslare Strand | Capital Works including rock armour revetment | | 14,290.46 |
Wexford | Rosslare Strand | Maintenance | 20,000 | 7,957.54 |
Wexford | Rosslare | New Scheme | | 155.38 |
Wexford | Cahore | Rock groynes, beach nourishment | | 43,286.42 |
Wexford | Rosslare | Revetment works | | 27,821.01 |
Wexford | Ballyconnigar | Rock revetment | | 22,239.00 |
Cork | Warren Strand | Beach Groynes | 120,000.00 | 120,000.00 |
Cork | Youghal | Coastal protection Phase , prep.contract docs. | 22,687.52 | 22,687.50 |
Cork | Warren Strand | Complete Phase 2 groyne | 41,623.31 | 41,623.31 |
Waterford | Tramore | Promenade Refurbishment | 20,700.00 | 17,572.30 |
Waterford | Cunnigar | Balance of 2001 grant | | 1,004.40 |
Dublin | Dublin City Council | Contribution to Risk Assessment Study | 80,000.00 | 80,000.00 |
Kerry | Ballyheigue | Road Protection Works | 150,000.00 | 150,000.00 |
Kerry | Ballyheigue | Complete Phase 1 | 225,000.00 | 225,000.00 |
Kerry | Ventry | Coastal protection works | 22,500.00 | 21,785.48 |
Kerry | Kenmare | Sea wall | 15,000.00 | 11,269.77 |
Wicklow | Brittas Bay | Update study, Extension of scheme | 37,500.00 | 37,351.79 |
Fingal | Burrow, Portrane | Repairs to embankment etc. | 7,500.00 | 7,500.00 |
Fingal | Portmarnock to Malahide | Repairs to Coastal walkway | 3,750.00 | 3,750.00 |
GENERAL PROJECTS | | | |
| | Coast Protection Strategy Study | 200,000.00 | 370,470.75 |
| GIS System | Maintenance & Customisation | 20,000.00 | 26,725.88 |
| Wave Buoy | Maintenance & Deployment | 10,000.00 | 0.00 |
Wicklow | Bray | Beach Monitoring | 15,000.00 | 4,646.40 |
| Basic Research | Tide Gauge Review Statistical analyses | 40,000.00 | 9,800.00 |
2004 Coast Protection Programme |
County | Location | Project | 2004 Allocation | 2004 |
| | | € | € |
Galway | Inishboffin | Emergency work | 262,500.00 | 144,932.87 |
Meath | Laytown | Laytown Study (Drogheda port material) | 30,000.00 | 30,000.00 |
Louth | Drogheda | Erosion of R167 | 26,000.00 | 28,986.00 |
Louth | Bellurgan | Erosion (Road) | 7,500.00 | 8,226.34 |
Louth | Cooley (Whitetown/ Ballagan) | Replacement of Rock Armour | 37,500.00 | 43,873.50 |
Louth | Annagassan,ËStrand Road | Concrete underpinning & rock armour | 112,500.00 | 112,499.13 |
Louth | Salterstown | County Road Erosion to road edge | 52,500.00 | 52,837.50 |
Mayo | Elly Bay | | | 24.45 |
Kerry | Kilfinora | Revetment works | 150,000.00 | 117292.49 |
Kerry | Baile an Rannaig,ËBurial Place | Provision of Rock Armour | 112,500.00 | 88,090.30 |
Dublin | Dún LaoghaireËRathdown CC | Coastal Survey | 18,000.00 | 19,239.00 |
Dublin | Corbawn Lane | Contract documents etc; | 22,500.00 | 30,855.00 |
Cork | Warren | Coast Protection works | 187,500.00 | 142,828.42 |
Cork | Youghal | Phase 1 | 375,000.00 | 379,458.88 |
Waterford | Helvic Pier | Emergency Works and Diving Survey | 90,000.00 | 70,902.76 |
Wexford | Courtown | Design of breakwaters etc; | 296,250.00 | 368,204.08 |
Wexford | Curracloe | Dune Protection | 56,250.00 | 31,030.92 |
Wicklow | Brittas Bay | Brittas Bay Study | 30,000.00 | 0.00 |
Wicklow | Greystones | Coast protection Site Investigation | 52,500.00 | 52,500.00 |
GENERAL PROJECTS | | Coast Protection Strategy Study | 248,000.00 | 174,220.62 |
| GIS System | Maintenance & Customisation | 40,000.00 | 31389.95 |
| Wave Buoy | Maintenance & Deployment | 15,000.00 | 45188.39 |
| Beach Monitoring | Monitoring of Nourished Beach at Bray | 15,000.00 | 16992.27 |
Basic Research | Tide Gauge | Installation of gauge for monitoring mean sea level | 60,000.00 | 11335.64 |
| Coastal Video Survey | Video Survey of National Coastline | 20,000.00 | 30991.5 |
| Detailed Survey of Selected Coastal Areas | Selected Coastal Areas | 40,000.00Ë | |
Wexford | Rosslare Maintenance | Beach and Compound Maintenance work | 60,000.00 | 83198.63 |
2005 Coast Protection Programme |
County | Location | Project | 2005 Allocation | 2005 |
| | | € | € |
Donegal | Curransport, Meenalaragh | Protection Works | 37,500.00 | 0.00 |
Donegal | Curransport, Meenalaragh | Protection Works | 15,000.00 | 52,500.00 |
Donegal | Gweebarra Bends | Protection to sea wall | 30,000.00 | 30,000.00 |
Donegal | Inver Village | Extension to protection wall | 37,500.00 | 52,500.00 |
Donegal | Inver Village | Extension to protection wall | 15,000.00 | 0.00 |
Donegal | Lagg | Beach Protection Works | 45,000.00 | 45,000.00 |
Donegal | Moville | Green amenity area and path | 4,500.00 | 4,500.00 |
Donegal | Rosbeg | Protection Works | 15,000.00 | 15,000.00 |
Donegal | Rye, Rathmullen | Protection Works | 105,000.00 | 105,000.00 |
Louth | Annagassan | Strand Road | 3,000.00 | 28,377.27 |
Louth | Salterstown | Road Protection Works | 63,750.00 | 48,193.50 |
Louth | Port Beach | Study | 11,250.00 | 11,253.00 |
Mayo | Bertra Beach, Westport | Protection Works | 75,000.00 | 75,000.00 |
Sligo | Mullaghmore | Dune Management Scheme | 11,250.00 | 11,340.75 |
Sligo | Rathlee | Coast Protection works | 45,000.00 | 31,352.88 |
Galway | Inishboffin | Design, tenders, etc for emergency works | 53,123.89 | 53,123.89 |
Galway | Inishboffin | Road Protection Works additional funding | 55,156.58 | 55,156.58 |
Donegal | *Aranmore | Protection Works | 18,750.00 | 31,875.00 |
Donegal | Aranmore | Protection works | 13,125.00 | 0.00 |
Donegal | *Maghery | Protection Works | 37,500.00 | 37,500.00 |
Donegal | *Muckross | Protection Works | 9,375.00 | 9,375.00 |
Galway | *Inishboffin | Road Protection Works | 75,000.00 | 75,000.00 |
Cork | Gyleen | Village Protection Works | 187,500.00 | 148,553.90 |
Cork | Youghal | Phase 1 completion | 225,000.00 | 232,892.50 |
Clare | Ross/Kilbaha | Installation of rock gabians & rock revetment | 75,000.00 | 88,987.50 |
Clare | Carrigaholt | Road Protection Works | 45,000.00 | 54,232.50 |
Kerry | Killelan Caherciveen | Road Protection Works | 15,000.00 | 15,000.00 |
Kerry | Baile an Rannaig | Provision of rock armour | 2,007.39 | 1,968.88 |
Dublin City Co. Co. | Merrion Gates | Provide banking/ramping to seal opening | 187,500.00 | 36,386.09 |
| Clontarf Promenade | Flood Defences Detailed Design | | 30,219.75 |
| Spencer Dock | Sea Surge Defence Barrier | | 120,894.16 |
Dún Laoghaire-Rathdown Co. Co. | Killiney | Repairs to beach gabions | 202,500.00 | 109,275.00 |
Dún Laoghaire-Rathdown Co. Co. | Corbawn/Shankill | Repairs to beach access | 101,250.00 | 29,947.50 |
Waterford | Bunmahon | Protection Works/Scheme Design | 30,000.00 | 17,825.77 |
Waterford | Cunnigar, Dungarvan | Protection Scheme/Design | 75,000.00 | 69,493.58 |
Wexford | Cahore | Continuation of Revetment works | 22,500.00 | 16,616.87 |
Wexford | Kilpatrick | Soft engineering Works to Beach | 15,000.00 | 15,271.43 |
Wicklow | Arklow | South Beach | 42,750.00 | 44,356.15 |
Wicklow | Bray to Greystones | Cliff path works | 138,750.00 | 69,665.25 |
Wicklow | Bray | Promenade flood prevention wall at Bray | 60,000.00 | 55,500.00 |
Kerry | Reen Ballinskelligs | Protection Works | 7,500.00 | 7,500.00 |
Wexford | Rosslare | Premliminary Design at Rosslare | 75,000.00 | 0.00 |
Wexford | Rosslare | Soft engineering Works to Beach | 22,500.00 | 10,118.96 |
Kerry | Maharees | Road Protection Works | 150,000.00 | 74,821.48 |
Kerry | Kilfenora | Rock Revetment | 25,546.88 | 21,100.12 |
GENERAL PROJECTS | | | | |
Coastal Protection | Strategy Study | | 200,000.00 | 132,816.27 |
Consultancy | Studies | | 100,000.00 | 0 |
GIS System | Customisation, Maintenance and training | 55,000.00 | 18,929.16 |
Wave Buoys | Maintenance and Deployment | 15,000.00 | 8,556.06 |
Beach Monitoring | Monitoring of Nourished beach at Bray, Co Wicklow | 10,000.00 | 4,646.40 |
Tide Guage | Installation of gauge for monitoring mean sea level | 40,000.00 | 19,723.00 |
Detailed Survey of Selected Coastal Areas | | 75,000.00 | 41,881.85 |
Rosslare Maintenance | | Rosslare maintenance works | 30,000.00 | 14,832.08 |
*Co-funded with Dept. Community, Rural and Gaeltacht Affairs — 37.5% each Dept. |
2006 Coast Protection Programme |
County | Location | Project | 2006 Allocation | 2006 |
| | | € | € |
Donegal | Bundoran Pier | Construction of retaining wall | 78,375.00 | 1,815.00 |
Donegal | Kincasslagh | Repairs to dunes system | 15,000.00 | 15,271.09 |
Louth | Port Beach | Study | 29,250.00 | 29,071.50 |
Louth | Annagassan | Rock revetment Phase 3 | 97,500.00 | 97,698.00 |
Meath | Bettystown-Laytown | Coastal Protection Study | 18,141.00 | 18,141.00 |
Meath | Laytown-Seafield Road | Coastal Protection Study | 9,000.00 | 2,723.00 |
Mayo | *Mulranny Beach | Repairs to causeway and bridge | 37,500.00 | 37,500.00 |
Galway | Inishboffin | Protection works | 450,000.00 | 500,034.63 |
Sligo | Dunmoran Strand | Work at Ardnaglass river | 337,500.00 | 35,344.93 |
Dublin City Council | Clontarf | Studies/advanced design/site investigations | 187,500.00 | 151,339.90 |
Fingal County Council | Portrane | Repairs to dunes at the Burrow | 75,000.00 | 0.00 |
Dún Laoghaire Rathdown | Killiney | Gabians at Killiney Beach | 215,981.00 | 294,342.46 |
Wicklow | The Murrough | Coastal Studies | 41,250.00 | 41,250.00 |
Wicklow | Bray | Flood prevention works to promenade | 4,500.00 | 4,500.00 |
Wicklow | Bray to Greystones | Protection works to cliff walk (cont.) | 69,085.00 | 0.00 |
Wicklow | Clogga Beach | Protection works at access | 52,500.00 | 52,500.00 |
Wexford | Courtown | Project planning & design stage for majorprotection scheme | 75,000.00 | 35,984.65 |
Wexford | Rosslare | Rock revetment | 375,000.00 | 368,615.63 |
Wexford | Ballinamona | Restore access to beach | 37,500.00 | 18,387.00 |
Wexford | Carne | Rock revetment | 108,000.00 | 108,108.80 |
Wexford | Rosslare | Study of coastal dynamics & protection requirements | 150,000.00 | 797.14 |
Wexford | St Helen's Bay | Rock revetment | 300,000.00 | 95,680.50 |
Waterford | Bonmahon | Reconstruction of sand dunes, protection works scheme design | 656,200.00 | 321,689.91 |
Waterford | Ballyquin | Rock armour and gabian wall | 75,000.00 | 0.00 |
Waterford | Cunnigar | Protection Works | 1,608.90 | 1,608.90 |
Waterford | Helvick Pier repairs | Cliff stabilisation | 187,500.00 | 87,530.74 |
Cork | Gyleen | Cliff protection works (cont'd) | 206,250.00 | 245,082.80 |
Kerry | Rossbeigh | Cliff & road prot. studies and design etc. | 15,000.00 | 5,082.00 |
Kerry | Maharees | Revetment works | 13,500.00 | 22,579.84 |
| Baile an Rannaig | | 12.24 |
Kerry | *Baile an Rannaig | Prot. to sand dunes in Smerwick Harb. | 26,250.00 | 26,086.39 |
Kerry | Cooncrome | Prot. works to car park | 18,750.00 | 0.00 |
Kerry | *Gleesk | Repairs and strengthen sea wall | 11,250.00 | 11,250.00 |
Kerry | Ballyteigue/Dromatoor | Cliff road protection works | 375,000.00 | 637,500.00 |
Clare | Cloghauninchy Beach Road | Sea Wall construction | 7,500.00 | 0.00 |
| Coastal Protection | Strategy Study | 225,000.00 | 204,135.07 |
| Detailed survey | of selected coastal areas | 450,000.00 | 266,560.99 |
| GIS system | | 40,000.00 | 19,178.50 |
| GIS maintenance & development | | | 593.65 |
| Student Engineer | | 40,000.00 | |
| Wave buoy and tide gauge deployment | | 55,000.00 | 2,501.92 |
Wexford | Rosslare | Maintenance | 45,000.00 | 5,492.92 |
*Co-funded with Dept. Community, Rural and Gaeltacht Affairs — 37.5% each Dept. |