Question 300: To ask the Minister for Transport when work will begin on footbridges over the railway line at Coolmine and Clonsilla stations; and when these bridges will be completed. [43539/06]
Martin Cullen (Waterford, Fianna Fail)
Link to this: Individually | In context
The provision and maintenance of footbridges over railway lines is a matter for Iarnród Éireann and not one in which I have any role. I understand however from Iarnród Éireann that tenders for the construction of the new footbridges at Coolmine and Clonsilla stations are due to be received by 18 December 2006 and the project programme provides for the bridges to be completed and in use by June 2007.