Written answers
Wednesday, 5 July 2006
Department of Communications, Energy and Natural Resources
Harbours and Piers
12:00 pm
Róisín Shortall (Dublin North West, Labour)
Link to this: Individually | In context
Question 52: To ask the Minister for Communications, Marine and Natural Resources if he will provide information on the €7.9 million funding for coastal protection and small harbours during 2006; if this funding will increase in 2007; and if he will make a statement on the matter. [26629/06]
John Browne (Wexford, Fianna Fail)
Link to this: Individually | In context
Under the Small Fishery Harbours Programme 2006 €4.186 million has been allocated for the improvement of facilities at small harbours and landing places with a key role in maintaining jobs in fishing, aquaculture and ancillary activities. €3.721 million has been allocated under the Coastal Protection Programme 2006 to address priority coast protection works around the coastline.
A number of the projects are being co-funded with the Department of Community, Rural and Gaeltacht Affairs and this Department under the CLÁR scheme. This scheme is to facilitate minor repairs and safety works on small piers, slipways and coastal erosion in CLÁR areas, including Gaeltacht areas and islands.
A list of projects under the Coastal Protection and the Small Harbours Programmes showing breakdown of funding is attached.
The financial envelope including funding requirements for the fishery harbours and coast protection measures under the NDP 2007-2013 is currently being formulated.
Small Harbours Programme 2006 | ||||
Project | Project Description | DCMNR Cost 75%/ 37.5% | Co-funded DCRGA 37.5% | Total cost 100% |
€000's | €000's | €000's | ||
Wexford | ||||
Courtown | Grouting and structural repairs to harbour wall | 37.5 | — | 50 |
Kilmore Quay | Site investigation to complement hydrographic survey | 135 | — | 180 |
Killurin Pier | Slipway reconstruction and safety works | 22.5 | — | 30 |
Slade Harbour | Structural improvements to old pier wall | 30 | — | 40 |
Cahore | Protection works | 18.75 | — | 25 |
Waterford | ||||
Ardmore Pier | Raising of the Deck Level | 12 | — | 16 |
Blackwater | Construction of slipway and turning circle | 45 | — | 60 |
Cork | ||||
Knockadoon | Redecking & reproofing of slipway | 75 | — | 100 |
Schull Pier | Relocation of services and new lighting | 33.75 | 33.75 | 90 |
Kerry | ||||
Caherciveen Pier | Additional fendering | 7.5 | 7.5 | 20 |
Renard | Repair and stabilisation of pier (study) | 75 | — | 100 |
Tarbert | Structural assessment | 8 | — | 10 |
Limerick | ||||
Kilteery | Surface decking | 19 | — | 25 |
Clare | ||||
Ballyvaughan | Pier Repairs | 44.625 | 44.625 | 119 |
Doonbeg | Pier extension and dredging (SI and design) | 22.5 | — | 30 |
Carrigaholt | Repairs to old pier & dredging | 64 | 64 | 170 |
Galway | ||||
Cleggan Pier | New Berthage & access (preliminary report) | 54.75 | — | 73 |
Blackweir, Maree | Holding tank & breakwater | 120 | — | 160 |
Rosroe | New key wall and slipway | 74.55 | 74.55 | 198.80 |
Ballyconnelly | Construction of access road | 60 | 60 | 160 |
Wallace Quay | Construction of access road, new deck slab and parapet wall | 75 | 75 | 200 |
Parkmore Pier, Kinvara | Essential repairs | 22.5 | — | 30 |
Mayo | ||||
Purteen | New development options study | 75 | — | 100 |
Newport | Repairs to quay and dredging | 37.5 | — | 50 |
Roigh pier | New Slipway | 75 | 75 | 200 |
Cloghmore | Re-deck old pier and structural improvements | 56.25 | 56.25 | 150 |
Sligo | ||||
Raghly Pier | Harbour Improvement works | 202.5 | — | 280 |
Donegal | ||||
Dungloe | Slipway and turning area | 67.5 | 67.5 | 180 |
Burtonport | Dredging | 585 | — | 780 |
Buncrana | Breakwater | 225 | — | 300 |
Woodquarter | Lighting | 7.5 | — | 10 |
Portnoo | Urgent safety works | 22.5 | — | 30 |
Arranmore, Stacamore Pier | Re-decking and mooring rings | 7.5 | 7.5 | 20 |
Donegal Town | Pontoons for small craft and waterbus with slipway extension | 150 | — | 200 |
Totals | — | 2,568.17 | 565.67 | 4,186.80 |
Coast Protection Programme 2006 | ||||
Project | Project Description | DCMNR Cost 75%/ 37.5% | Co-funded DCRGA 37.5% | Total cost 100% |
€000's | €000's | €000's | ||
Louth | ||||
Port Beach | Study | 29.25 | — | 39 |
Annagasssan | Rock revetment Phase 3 (Continuation) | 97.5 | — | 130 |
Meath | ||||
Mornington | Armour Protection | 75 | — | 100 |
Bettystown-Laytown | Coastal Protection Study | 9 | — | 12 |
Laytown-Seafield Road | Coastal Protection study | 9 | — | 12 |
Dublin (Fingal) | ||||
Portrane | Repairs to dunes at the Borrow | 75 | — | 100 |
Dublin City Council | ||||
Clontarf | Studies/advanced design/site investigations | 187.5 | — | 250 |
Dún Laoghaire-Rathdown | ||||
Killiney | Gabions at Killliney Beach (continuation) | 215.981 | — | 287.975 |
Wicklow | ||||
The Murrough | Coastal Studies | 41.25 | — | 55 |
Bray | Flood prevention works work to promenade | 4.5 | — | 6 |
Bray to Greystones | Protection works to cliff walk (continuation) | 69.085 | — | 92.113 |
Wexford | ||||
Courttown | Project planning and design stage for major protection scheme | 75 | — | 100 |
Rosslare | Rock revetment | 375 | — | 500 |
Ballinamona | Restore access to beach | 37.5 | — | 50 |
Carne | Rock revetment | 75 | — | 100 |
Rosslare | Study of coastal dynamics and protection requirements | 150 | — | 200 |
Rosslare | Maintenance work at Rosslare Strand | 45 | — | 45 |
Waterford | ||||
Bonmahon | Reconstruction of sand dunes Protection works scheme design | 656.2 | — | 875 |
Ballyquin | Rock armour and Gabion wall | 75 | — | 100 |
Cork | ||||
Glyeen | Cliff protection works (Continuation) | 206.25 | — | 275 |
Kerry | ||||
Rossbeigh | Cliff and road protection studies and design. Linked to dredging at Cromane Pier project | 15 | — | 20 |
Maharees | Revetment works | 14 | — | 18 |
Baile an Rannaig | Protection to sand dunes in Smerwick Harbour | 26.25 | 26.25 | 70 |
Cooncrome | Protection works to car park | 18.75 | 18.75 | 50 |
Gleesk | Repairs and strengthen sea wall | 11.25 | 11.25 | 30 |
Mayo | ||||
Mulranny Beach | Repairs to causeway and bridge | 37.5 | 37.5 | 100 |
Donegal | ||||
Bundoran | Construction of retaining wall | 78.375 | — | 104.500 |
Total | 2,709.94 | 93.75 | 3,721.588 |