Question 474: To ask the Minister for Education and Science if her Department has received an amended cost plan as part of the school building programme for a school (details supplied) in County Carlow; the stage they are at in the school building programme; and when she expects a decision to be made which would allow same to advance to the next stage. [15971/06]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

The building project in question was one of 40 major school building projects listed in my announcement of 25 April 2006 to proceed to tender and construction.

My officials have recently received an updated cost plan to complete the stage 3 submission (detailed plans/costs) for the project. This will be examined as soon as possible and my officials will then be in further contact with the School Authorities with regard to the next steps involved in progressing this project.