Question 87: To ask the Minister for Education and Science the number of the Adamstown schools which are planned to be opened within the next two years; when the remainder are planned to be opened; and if she will make a statement on the matter. [13441/06]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

The first primary school will commence operation in Adamstown in September 2007. This is in line with the phasing arrangement set out in the strategic development zone planning scheme. The remaining schools are due to be delivered at the end of phases four, six and eight of the scheme. The precise timing of these is dependent on the rate and pace of the delivery of the housing phases themselves.