Written answers
Wednesday, 15 February 2006
Department of Education and Science
School Accommodation
9:00 pm
Bernard Durkan (Kildare North, Fine Gael)
Link to this: Individually | In context
Question 285: To ask the Minister for Education and Science if she has received detailed plans or costs in respect of the provision of required facilities at a school (details supplied) in County Kildare; and if she will make a statement on the matter. [5994/06]
Mary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context
My Department's officials wrote to the school authorities in October 2005 giving approval to proceed to stage three, detailed plans and costs, of architectural planning. Pending receipt in my Department of the stage three submission from the school authorities no further progression can be made on this project.
Bernard Durkan (Kildare North, Fine Gael)
Link to this: Individually | In context
Question 286: To ask the Minister for Education and Science if she will report on progress in the matter of extra facilities required at a school (details supplied) in County Kildare; if the amended stage two report has been completed; and if she will make a statement on the matter. [5995/06]
Mary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context
In December 2005 my officials requested the school authorities to submit a revised sketch scheme as an addendum to the original stage two report, developed sketch scheme. This has recently been received and is being examined by my officials. When the assessment is complete they will be in further contact with the school authorities.
Bernard Durkan (Kildare North, Fine Gael)
Link to this: Individually | In context
Question 287: To ask the Minister for Education and Science if the report in respect of a school (details supplied) in County Kildare has been fully examined in her Department; if she expects to commence progress at an early date; and if she will make a statement on the matter. [5996/06]
Mary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context
Tenders for this project were returned in late October and the tender report was received in my Department in late December. Examination of the report by my Department's technical staff is nearing completion. My Department will be in contact with the school management as soon as possible.
No comments