Question 384: To ask the Minister for Transport the moneys which have been received for the TENs programme since 1999; and the breakdown on a county or regional basis (details supplied). [33935/05]
Martin Cullen (Waterford, Fianna Fail)
Link to this: Individually | In context
Further to my answer to the Deputy's Questions Nos. 273 and 274 of 9 November 2005, the moneys received under the Trans-European Transport Networks, TEN-T, programme are set out in the following table, broken down by year and by project.
The TEN-T receipts on the N8 Cashel bypass project relate to the south-east region and the receipts on the N1 Dundalk to Border with Northern Ireland project relate to the Border region.
As regards the other five TEN-T projects listed in the attached table that are not specific to a NUTS 3 region, it is not possible to give a breakdown of the receipts at NUTS 3 level. This is because the grant approved by the Commission is approved for a project as a whole and is not broken down on a section by section basis, so it is not possible to say how much of the TEN-T grants paid by the Commission relate to a specific NUTS 3 region.
Table showing receipts under TENs Programme. | ||||||
Project | 2000-2001 | 2002 | 2003 | 2004 | 2005 (to 11.11.05) | Total Receipts 2000 to 11.11.05 |
€'000 | €'000 | €'000 | €'000 | €'000 | €'000 | |
Planning & Design of Ireland element of Irl/UK/Benelux road link (Cork-Dublin-Belfast) | Nil | 5,500 | 4,000 | Nil | 8,000 | 17,500 |
N8 Cashel Bypass | Nil | Nil | Nil | Nil | 720 | 720 |
N1 Dundalk to Border with Northern Ireland | Nil | Nil | Nil | Nil | 1,320 | 1,320 |
INSTANT (Information & Management System for Multimodal Transport in the Republic of Ireland and Northern Ireland) | Nil | 699 | Nil | Nil | Nil | 699 |
STREETWISE (Seamless Travel Environment for Efficient Travel in the Western Isles of Europe) | Nil | 51 | Nil | 75 | 145 | 271 |
Safety and upgrade work in conventional TENs Rail routes | 1,200 (received in year 2000) | Nil | Nil | 1,800 | Nil | 3,000 |
Elimination of key Permanent Speed Restrictions on the Cork-Dublin-Belfast Rail Corridor | Nil | Nil | Nil | Nil | 500 | 500 |
Total All Projects | 1,200 | 6,250 | 4,000 | 1,875 | 10,685 | 24,010 |