Question 536: To ask the Minister for Finance the amount spent to date on the agreed schedule of works for Lucan Demesne; the amount to be spent up to 31 December 2005; and if he will allow the balance of the €4.7 million to be spent in 2006. [25920/05]

Tom Parlon (Laois-Offaly, Progressive Democrats)
Link to this: Individually | In context

Total expenditure of €2.749 million has been incurred to date on the agreed schedule of works for Lucan Demesne. It is expected that the balance of the funding will be spent in 2006-2007 on receipt of the appropriate certification of expenditure from the local authorities involved.