Written answers

Thursday, 30 June 2005

8:00 pm

Photo of Finian McGrathFinian McGrath (Dublin North Central, Independent)
Link to this: Individually | In context

Question 415: To ask the Minister for Transport if he will give an update on the completion of the Dublin Port tunnel. [23683/05]

Photo of Martin CullenMartin Cullen (Waterford, Fianna Fail)
Link to this: Individually | In context

The planning, design and implementation of national road improvement projects, including the Dublin Port Tunnel, is a matter for the National Roads Authority — NRA — and the local authorities concerned. I understand from the NRA that the primary construction work on the port tunnel is expected to be completed in December 2005 and that the tunnel will be open to traffic early in 2006, following commissioning of the tunnel's operations and safety features.

Comments

No comments