Written answers

Wednesday, 26 January 2005

Department of Education and Science

Schools Building Projects

9:00 pm

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 823: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34331/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 839: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34347/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 866: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34374/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 871: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34379/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 914: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34422/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 985: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34493/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1054: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34562/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

I propose to take Questions Nos. 823, 839, 866, 871, 914, 985 and 1054 together.

The projects referred to by the Deputy were listed to proceed to tender and construction as part of the 2004 school building programme. These projects did not proceed as quickly as envisaged due mainly to issues relating to planning permission, design teams being slower than anticipated in progressing projects and the need to revise briefs with reference to special needs requirements. It is envisaged that these projects will proceed as quickly as possible in 2005.

The day-to-day management of projects is a matter for each school and their design teams. The specific information requested by the Deputy is not readily available in my Department in the format requested by him.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 824: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34332/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 829: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34337/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 830: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34338/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 853: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34361/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 855: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34363/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 858: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34366/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 860: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34368/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 873: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34381/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 874: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34382/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 875: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34383/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 885: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34393/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 886: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34394/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 887: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34395/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 890: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34398/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 891: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34399/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 892: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34400/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 893: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34401/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

I propose to take Questions Nos. 824, 829, 830, 853, 855, 858, 860, 873 to 875, inclusive, 885 to 887, inclusive, 890 to 893, inclusive, together.

Construction is under way on the projects referred to by the Deputy. It is envisaged that many of these projects will be completed in the latter half of 2005.

The day-to-day management of projects is a matter for each school authority and their design teams. The specific information requested by the Deputy in relation to each project is not readily available in my Department in the format requested by him.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 825: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34333/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 834: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34342/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 838: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34346/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 845: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34353/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 846: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34354/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 847: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34355/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 848: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34356/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 849: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34357/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 863: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34371/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 864: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34372/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 880: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34388/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 911: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34419/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 917: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34425/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 925: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34433/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 927: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34435/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 928: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34436/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 929: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34437/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 935: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34443/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 950: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34458/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 954: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34462/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 957: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34465/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 958: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34466/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 961: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34469/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 967: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34475/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 984: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34492/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

I propose to take Questions Nos. 825, 834, 838, 845 to 849 inclusive, 863, 864, 880, 911, 917, 925, 927 to 929 inclusive, 935, 950, 954, 957, 958, 961, 967 and 984 together.

As part of the expansion of the devolved schemes initiatives for primary school building works the schools referred to by the Deputy were allocated a predetermined grant to enable the school management authorities to provide additional accommodation and/or improvements works.

The initiatives facilitate the boards of management by allowing them to address their accommodation and building priorities. It also provides a guaranteed amount of funding and gives boards of management control and responsibility for the building project.

As the initiatives are devolved it is the responsibility of each school management authority to determine the date the project proceeds to tender, the date the tender is accepted, the duration of the contract period and most importantly to manage the post contract control in respect of both costs and provision.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 826: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34334/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 827: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34335/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 828: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34336/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 831: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34339/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 832: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34340/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 835: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34343/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 841: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34349/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 842: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34350/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 843: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34351/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 844: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34352/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 862: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34370/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 867: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34375/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 868: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34376/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 869: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34377/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 870: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34378/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 877: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34385/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 878: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34386/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 879: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34387/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 881: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34389/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 883: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34391/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

I propose to take Questions Nos. 826 to 828, inclusive, 831, 832, 835, 841 to 844, inclusive, 862, 867 to 870, inclusive, 877 to 879, inclusive, 881 and 883 together.

Construction is well under way on the projects referred to by the Deputy. It is envisaged that these projects will be completed in the latter half of 2005.

The day-to-day management of projects is a matter for each school and their design teams. The specific information requested by the Deputy in relation to each project is not readily available in my Department in the format requested by him.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 833: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34341/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 851: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34359/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 852: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34360/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 854: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34362/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 859: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34367/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 872: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34380/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 888: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34396/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 889: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34397/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 903: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34411/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 905: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34413/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 910: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34418/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 946: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34454/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 997: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34505/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1016: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34524/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1030: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34538/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1042: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34550/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1052: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34560/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1059: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34567/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1060: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34568/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1062: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34570/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

I propose to take Questions Nos. 833, 851, 852, 854, 859, 872, 888, 889, 903, 905, 910, 946, 997, 1016, 1030, 1042, 1052, 1059, 1060 and 1062 together.

Construction is completed on all of the projects referred to by the Deputy. All of these projects commenced construction prior to 2004.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 836: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34344/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 840: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34348/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 882: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34390/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 899: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34407/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 915: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34423/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 916: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34424/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 936: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34444/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 937: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34445/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1031: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement in the matter. [34539/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1063: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34571/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

I propose to take Questions Nos. 836, 840, 882, 899, 915, 916, 936, 937, 1031 and 1063 together.

The projects referred to by the Deputy were listed to proceed to tender and construction as part of the 2004 school building programme. The tendering process is either under way or completed on these projects and it is envisaged that they will proceed to construction as early as possible in 2005.

The day-to-day management of projects is a matter for each school and their design teams. The specific information requested by the Deputy in relation to each project is not readily available in my Department in the format requested by him. In broad terms there are many reasons which can cause unexpected delays in the pace at which some projects advance. These include an appeal of planning permission by third parties to An Bord Pleanála, contractors withdrawing tenders and design teams being slower than anticipated in getting projects tendered.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 837: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34345/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 850: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34358/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 865: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34373/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 908: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34416/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 938: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34446/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 943: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34451/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 962: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34470/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 966: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34474/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 970: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34478/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 972: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34480/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 977: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34485/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 981: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34489/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 996: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34504/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1003: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34511/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1015: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34523/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1022: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34530/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1024: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34532/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1025: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34533/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1036: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34544/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1041: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34549/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1056: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34564/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

I propose to take Questions Nos. 837, 850, 865, 908, 938, 943, 962, 966, 970, 972, 977, 981, 996, 1003, 1015, 1022, 1024, 1025, 1036, 1041 and 1056 together.

Construction is completed on all of the projects referred to by the Deputy. Most of these projects commenced construction prior to 2004.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 856: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34364/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

The current position relating to proposed works at the school referred to by the Deputy is that the school applied for and was successful in securing funding under the 2004 summer works scheme, SWS, for the first phase of the replacement of the roof. This was completed in 2004. An application under the 2005 SWS has been received from the school management for the second phase of roof replacement. As I outlined in early December, when setting out details of the schools building and modernisation programme, I will announce in February details of the schools that will receive funding based on the applications being processed by my officials.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 857: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34365/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

My Department is in consultation with the school authority referred to by the Deputy regarding the delivery of this project. Documentation received in December from the school's design team is being reviewed. Officials in the school building section of my Department will communicate with the school authority shortly.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 861: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34369/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

Tenders for the project to which the Deputy refers were not agreed and, therefore, work did not start. The original plan was to locate this project on a greenfield site. Since then other options have been considered. When a decision is made on the most appropriate delivery method for this project, I will inform the parties concerned.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 876: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34384/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 901: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34409/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 904: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34412/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 906: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34414/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 923: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34431/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 932: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34440/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 960: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34468/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 975: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34483/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 976: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34484/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 983: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34491/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1005: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34513/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1008: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34516/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1061: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34569/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1065: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34573/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

I propose to take Questions Nos. 876, 901, 904, 906, 923, 932, 960, 975, 976, 983, 1005, 1008, 1061 and 1065 together.

The projects referred to by the Deputy were listed to proceed to tender and construction as part of the 2004 school building programme. These projects did not proceed as quickly as envisaged due mainly to issues relating to planning permission, sites or design teams being slower than anticipated in progressing projects. It is envisaged that these projects will proceed as quickly as possible in 2005. The day-to-day management of projects is a matter for each school authority and their design teams. The specific information requested by the Deputy is not readily available in my Department in the format requested by him.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 884: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34392/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 895: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34403/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 896: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34404/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 897: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34405/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 898: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34406/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 907: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34415/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 909: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34417/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 912: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34420/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 913: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34421/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 918: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34426/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 919: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34427/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 921: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34429/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 924: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34432/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 926: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34434/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 930: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34438/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 933: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34441/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 934: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34442/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 939: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34447/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 940: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34448/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 941: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34449/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

I propose to take Questions Nos. 884, 895 to 898, inclusive, 907, 909, 912, 913, 918, 919, 921, 924, 926, 930, 933, 934, 939, 940 and 941 together.

Construction on the projects referred to by the Deputy commenced in 2004. It is envisaged that most of these projects will be completed in the latter half of 2005. The day-to-day management of projects is a matter for each school and its design team. The specific information requested by the Deputy regarding each project is not available in my Department in the format requested by him.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 894: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34402/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 900: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34408/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 902: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34410/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 922: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34430/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 931: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34439/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 947: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34455/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 948: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34456/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 951: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34459/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 952: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34460/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 953: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34461/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 956: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34464/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 974: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34482/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1006: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34514/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1007: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34515/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1037: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34545/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1038: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34546/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1051: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34559/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

I propose to take Questions Nos. 894, 900, 902, 922, 931, 947, 948, 951, 952, 953, 956, 974, 1006, 1007, 1037, 1038 and 1051 together.

Construction is under way on the projects referred to by the Deputy. It is envisaged that many of these projects will be completed in the latter half of 2005.

The day-to-day management of projects is a matter for each school authority and their design teams. The specific information requested by the Deputy with regard to each project is not readily available in my Department in the format requested by him.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 920: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34428/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 986: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34494/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 988: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34496/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 990: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34498/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 992: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34500/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 994: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34502/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1000: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34508/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1017: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34525/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1021: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34529/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1023: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34531/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1032: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34540/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1033: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34541/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1039: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34547/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1040: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34548/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1058: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34566/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

I propose to take Questions Nos. 920, 986, 988, 990, 992, 994, 1000, 1017, 1021, 1023, 1032, 1033, 1039, 1040 and 1058 together.

As part of the expansion of the devolved schemes initiatives for primary school building works, the schools referred to by the Deputy were allocated a predetermined grant to enable the school management authorities to provide additional accommodation and-or improvements works. The initiatives facilitate the boards of management by allowing them to address their accommodation and building priorities. It also provides a guaranteed amount of funding and gives boards of management control and responsibility for the building project.

As the initiatives are devolved, it is the responsibility of each school management authority to determine the date the project proceeds to tender, the date the tender is accepted, the duration of the contract period and most importantly to manage the post contract control in respect of both costs and provision.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 942: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if the project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34450/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 944: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34452/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 945: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34453/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 949: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34457/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 955: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34463/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 959: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34467/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 963: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34471/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 964: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34472/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 965: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34473/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 968: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34476/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 969: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34477/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 971: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34479/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 973: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34481/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 978: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34486/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 979: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34487/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 982: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34490/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 987: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34495/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 989: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34497/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 991: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34499/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 993: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34501/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

I propose to take Questions Nos. 942, 944, 945, 949, 955, 959, 963, 964, 965, 968, 969, 971, 973, 978, 979, 982, 987, 989, 991 and 993 together.

Construction on the projects referred to by the Deputy commenced in 2004 and it is envisaged that these projects will be completed in the latter half of 2005. The day-to-day management of projects is a matter for each school and their design teams. The specific information requested by the Deputy on each project is not readily available in my Department in the format requested by him.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 980: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34488/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

The authorities of the school in question were offered grant aid under the 2004 devolved permanent accommodation initiative to provide additional permanent classroom accommodation but declined to take part in the scheme.

The level of accommodation required at the school is currently being reassessed by the planning section of my Department. The school authorities will be contacted on the matter in due course.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 995: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34503/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 998: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34506/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 999: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34507/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1001: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34509/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1002: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34510/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1004: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34512/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1009: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34517/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1010: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34518/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1011: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34519/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1012: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34520/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1013: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34521/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1014: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34522/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1018: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34526/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1019: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34527/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1020: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34528/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1026: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34534/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1027: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34535/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1028: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34536/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1029: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34537/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

I propose to take Questions Nos. 995, 998, 999, 1001, 1002, 1004, 1009 to 1014, inclusive, 1018 to 1020, inclusive, and 1026 to 1029, inclusive, together.

Construction is well under way on the projects referred to by the Deputy. It is envisaged that these projects will be completed in the latter half of 2005.

The day-to-day management of projects is a matter for each school and their design teams. The specific information requested by the Deputy in regard to each project is not readily available in my Department in the format requested by him.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1034: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34542/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1035: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34543/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1043: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34551/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1044: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34552/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1045: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34553/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1046: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34554/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1047: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34555/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1048: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34556/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1049: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34557/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1050: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34558/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1055: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34563/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1057: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34565/04]

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1064: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34572/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

I propose to take Questions Nos. 1034, 1035, 1043 to 1050, inclusive, 1055, 1057 and 1064 together.

Construction on the projects referred to by the Deputy commenced in 2004 and it is envisaged that these projects will be completed in the latter half of 2005.

The day-to-day management of projects is a matter for each school and its design team. The specific information requested by the Deputy in regard to each project is not readily available in my Department in the format requested by him.

Paul McGrath (Westmeath, Fine Gael)
Link to this: Individually | In context

Question 1053: To ask the Minister for Education and Science the date on which the tenders for a project (details supplied) were agreed; the date on which work started on the project; the reason for delays between these respective dates; the estimated construction period; if this project is on schedule; if it is behind schedule; if behind schedule, the reason for the delays; and if she will make a statement on the matter. [34561/04]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

The school referred to by the Deputy was listed as a refurbishment-extension project for proceeding to tender and construction as part of the 2004 school building programme. Following discussions and correspondence with the Department, the board of management has advised the Department that it will purchase a site for a new school provided the project is changed to a new school. The Department has agreed to facilitate this request being explored provided it can be achieved within the existing budget set for the project.

The Department has made it clear to the board of management that the onus is on it to explore the new school option within an indicative timescale set by the Department. It is envisaged that interaction with the Department will be kept to a minimum. However, in the event of it not proving possible to progress the new school option for reasons such as site acquisition, budget issues etc., the project will revert back to a refurbishment-extension of the existing school. The board of management has accepted this and is currently working on the acquisition of a site following which they have been authorised to engage a design team to commence design work on the school.

Photo of Phil HoganPhil Hogan (Carlow-Kilkenny, Fine Gael)
Link to this: Individually | In context

Question 1067: To ask the Minister for Education and Science the names of all primary and post primary schools that are the subject of an application for financial resources to extend, amalgamate or construct a new school for Counties Carlow and Kilkenny; and if she will make a statement on the matter. [1043/05]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

The information sought by the Deputy is not readily available in my Department. However, if the Deputy has a query about any specific school, I would be happy to provide the information for him.

Comments

No comments

Log in or join to post a public comment.