Written answers

Tuesday, 12 October 2004

Department of Health and Children

Irish Blood Transfusion Service

9:00 pm

Photo of Kathleen LynchKathleen Lynch (Cork North Central, Labour)
Link to this: Individually | In context

Question 251: To ask the Tánaiste and Minister for Health and Children if development of the interim facility for the Irish Blood Transfusion Service on the St. Finbarr's Hospital site in Cork has commenced; if the development will be complete on schedule, by December 2004; and if she will make a statement on the matter. [24412/04]

Photo of Mary HarneyMary Harney (Dublin Mid West, Progressive Democrats)
Link to this: Individually | In context

The design team for the interim facility for the Irish Blood Transfusion Service in Cork was appointed early in 2004. Procurement of the facility is being fast-tracked and construction work commenced on site in June 2004. The contract is being carried out in two phases to allow continuity of the existing service. Phase 1, the new interim laboratory building, is complete including commissioning, occupation and live testing. Construction work on phase 2, redevelopment of the existing laboratory building and donor clinic, has commenced and is currently on programme for completion in early December 2004.

Comments

No comments

Log in or join to post a public comment.