Dáil debates

Thursday, 1 June 2017

5:05 pm

Photo of Aindrias MoynihanAindrias Moynihan (Cork North West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

10. To ask the Minister for Public Expenditure and Reform when flood defence construction works will advance in Baile Mhúirne and Ballymakeera. [26237/17]

Photo of Aindrias MoynihanAindrias Moynihan (Cork North West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I have repeatedly raised the concerns of residents in Baile Mhúirne and Baile Mhic Íre about the risk of flooding from the River Sullane. I have raised the matter a number of times in the Dáil Chamber. The residents need to see progress on the scheme. There was an exhibition in 2011 and designs were to be advanced during 2014. The questions about freshwater pearl mussels were addressed last year, yet there does not seem to be a plan in place. What is the up-to-date position? How soon will the much-needed scheme advance towards construction and when will residents in Baile Mhúirne and Baile Mhic Íre have peace of mind regarding the risk of flooding?

Photo of Paschal DonohoePaschal Donohoe (Dublin Central, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I am advised by the Commissioners of Public Works that the Baile Mhúirne and Ballymakeera scheme is at outline design stage, on which the preferred options for the scheme are being finalised. The River Sullane has a history of containing freshwater pearl mussels which have protected status as an Annex II listed species under the EU habitats directive. An environmental survey was carried out to establish the status of the population and the likely impact of works. Given the impact the proposed works could have on the freshwater pearl mussel population, a solution to avoid damage was illustrated and submitted to the Department of Arts, Heritage, Regional, Rural and Gaeltacht Affairs. The submission was approved, allowing the scheme preparations to progress to site investigations where the results will inform the preferred options for the scheme.

To respond to the Deputy's specific question, tenders have been received for a site investigation contractor, with the contract expected to be placed in June 2017, or this month. It is proposed to hold a second public information day, followed by a public exhibition of the preferred scheme this year.

When these stages are successfully completed, provided the proposals are broadly accepted by the public and the stakeholders and the scheme is technically, environmentally and economically viable, the scheme will proceed to detailed design stage and formal confirmation by the Minister for Public Expenditure and Reform under the Arterial Drainage Acts 1945 and 1995 following which construction can commence.

My office continues to liaise with Cork County Council and local representatives on this scheme. As I said, I expect the site investigation contractor to be in place this month.

5:15 pm

Photo of Aindrias MoynihanAindrias Moynihan (Cork North West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

It is positive news that the site investigations will happen later this summer. However, when I raised the question late last year, the Department of Arts, Heritage, Regional, Rural and Gaeltacht Affairs had agreed a solution on the way forward for the freshwater pearl mussel. It was proposed that there would be a second public information day and exhibition this year as well as detailed design. Is the detailed design slipping at this stage? Is it envisaged that the detailed design will commence this year and that we will be in a position to move towards tendering and construction for the overall scheme later this year or early next year? Can the Minister clarify that? Is it the case that there is still a cost-benefit analysis to be conducted on this scheme, and is the risk still there that it could delay the scheme further?

Photo of Paschal DonohoePaschal Donohoe (Dublin Central, Fine Gael)
Link to this: Individually | In context | Oireachtas source

With regard to the different questions the Deputy has put to me, due to the presence of the pearl mussel in some stretches of the river and its protected status, the scheme could not progress, which was the Deputy's point, until a proposal was submitted to the National Parks and Wildlife Service, NPWS. This was submitted in June of last year. The NPWS responded by stating that it had no comment or objection to the proposal. Following this, a desktop survey has been undertaken on the relocation of the mussels to inform the next steps. In terms of the timing of what will happen, as I have said to the Deputy and as he has acknowledged, the contract is expected to be in place this month. The site investigation will provide information on the channel to decide on the preferred options to progress the scheme. It is expected that this will take three months. I assume the second public information day will then take place after that.

Photo of Aindrias MoynihanAindrias Moynihan (Cork North West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Arís is arís eile, táim tar éis an cheist mar gheall ar na tuilte i mBaile Bhuirne agus i mBaile Mhic Íre a tharraingt os comhair na Dála. Tá géarghá leis an obair seo a bhrú chun cinn agus faoiseamh a thabhairt do mhuintir na háite. I dtreo deireadh 2011, chonaiceamar na tuairiscí faoi agus bhí dearadh le bheith déanta in 2014. An féidir an rud seo a bhrú ar aghaidh agus faoiseamh a thabhairt do mhuintir Bhaile Bhuirne ó na tuilte sa Sulán? The Lee CFRAM was a pilot for the whole country. Baile Bhuirne was the most advanced in that scheme at the time. Right around the country, we have seen so many other schemes advancing so far ahead of the people who are in the pilot. If we can quickly advance through the final design, can the Minister give a commitment that he will prioritise funding and have construction of this overall scheme advance as quickly as possible?

Photo of Dara CallearyDara Calleary (Mayo, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

In the context of flooding, can the Minister confirm if the transfer of the Ministry responsible for flooding from the Minister of State, Deputy Canney, to Deputy Moran will happen?

Photo of Paschal DonohoePaschal Donohoe (Dublin Central, Fine Gael)
Link to this: Individually | In context | Oireachtas source

There are two questions there. From a funding point of view, €74,000 has been expended on this project to date. The project budget will be finalised before exhibition, but we expect that the approximate cost of this will be around €3 million. I can confirm to Deputy Moynihan that this is included in the financial profile of the OPW up to 2020. Assuming that the cost is in line with that, the OPW will be in a position to go ahead with that work. I understand the need for this work in the community and I know of the damage that has been caused by flooding in the past.

With regard to Deputy Calleary's question, the changeover in officeholder will take place at midnight tomorrow night.