Jennifer Whitmore (Wicklow, Social Democrats) | Oireachtas source
No. That was for 200 MW. This one states that 400 MW in additional temporary emergency generation should be sought to address the remainder of this gap. This was last September. It states that the 200 MW had already been procured, that an additional 450 MW would need to be procured and that the cost of that would be €40.