As the Deputy is aware, the National Transport Authority's, NTA, transport strategy for the greater Dublin area 2016-2035 proposes implementation of the overall DART expansion programme. In the Government’s budgetary framework for capital investment, Building on Recovery: Infrastructure and Capital Investment 2016-2021, funding was allocated to progress a number of key public transport projects in the NTA's strategy, including the DART expansion programme.

The DART expansion programme has a key role to play in delivering an efficient transport system. When fully implemented, the enhancements to the heavy rail system provided for in the NTA's transport strategy will create a full metropolitan area DART network for Dublin with all of the lines linked and connected. This integrated rail network will provide the core high capacity transit system for the region and will deliver a very substantial increase in peak-hour capacity on all lines from Drogheda, Maynooth, Hazelhatch and Greystones.

The original cost of the overall DART expansion programme, including the DART underground tunnel element, was estimated, as the Deputy will be well aware from his own experience, at €4 billion, of which €3 billion was in respect of the tunnel as originally designed. The Government decided in September 2015 that the original proposal for the tunnel should be redesigned to provide a lower cost solution. I understand that the NTA is working with Irish Rail on a revised proposal that is expected to be completed soon.

In the meantime, significant investment to upgrade signalling and turn-back facilities in the critical city centre area allowed the upgrade and reopening of the Phoenix Park tunnel in 2016. At the time of its opening, the NTA stated that the opening of the tunnel was an opportunity in the short term, at modest cost, to bring commuters from the west and south west to the city centre and the business district in the south of the city. It stated also that the opportunity of developing the DART underground is to be protected for the future.

The upgrade to the Phoenix Park tunnel in 2016 at a cost of €13.5 million has seen commuters on the Kildare to Dublin Heuston line benefit from having the option of direct trains to Connolly, Tara Street, Pearse and Grand Canal Dock stations.

Additional information not given on the floor of the House

Following the mid-term review of capital priorities, budget 2018 increased the multi-annual capital investment funding envelopes for the coming four-year period, including providing an enhanced capital envelope of €2.7 billion for Ireland's public transport investment between 2018 and 2021. This enhanced capital envelope includes funding in the order of €230 million for mainline rail and DART capacity enhancement and will allow acceleration of the initial stages of the overall DART expansion programme, focusing particularly at this stage on providing additional fleet to enhance capacity and extending the electrified DART system. Specifically, it will allow substantial progress on electrification of the Northern rail line as far as Balbriggan, now expected to be delivered in 2022, and commencing work on the Maynooth line.

Planning for longer term investment will form part of the national development plan, the Government's overall ten-year investment plan which we will be launching later this week alongside the new national planning framework for the period to 2040.