I am addressing this matter this evening on behalf of my colleague, the Minister for Communications, Marine and Natural Resources, Deputy Noel Dempsey. On the question of the quantified risk assessment referred to by the Minister in a reply to a parliamentary question raised by Deputy Cowley and answered on 9 February last, the assessment to which he was referring was not the Johnson report which the Deputy understood it to be. It was a quantified risk assessment report commissioned by the then developers in 2001, namely, Enterprise Energy Ireland Limited, on the onshore pipeline.

A risk is an expression which combines the probability of an event and the consequences of that event. The qualified risk assessment looks at the specifics of the pipeline and of the area the pipeline goes through using statistical data to determine the risks associated with failure. The quantified risk assessment addresses the risks present during the operational phase of the onshore section of the pipeline, that is, the section of the pipeline between the mean low water mark and the first isolation valve upstream of the pig trap in the onshore terminal.

As regards the Minister being satisfied that a quantified risk assessment has been carried out on the onshore sections of the Corrib gas pipeline, that is the case and a copy has been made available to the Department. The quantified risk assessment undertaken for the onshore section of the pipeline, which was intended to identify and assess all risks associated with the operation of the onshore section of the pipeline, included a detailed analysis of the risk of damage to the pipeline and consequences of any such damage.

The report makes recommendations for risk reduction where appropriate and will seek to demonstrate that the residual risks associated with the operation of the onshore pipeline have been reduced to tolerable levels. It showed that even in the worst case of the pipeline being ruptured and the gas being ignited, the occupants of a building 70 m away would be safe. The design of the pipeline means that the risk of such an event or any other type of gas escape is infinitesimally small.

Following receipt of the developers' pipeline consent to construct application, the Minister's predecessor commissioned a pipeline expert, Mr. Andrew Johnson, to carry out a further independent technical evaluation on the information supplied by the developers. Mr. Johnson's report suggested certain updating of the company's quantified risk assessment and the developers duly agreed to carry this out.

Mr. Johnson's report was entitled Report on the Evaluation of the On-shore Pipeline Design Code, and makes a number of recommendations for risk reduction where appropriate. Mr. Johnson's study addressed design, methodology, operating conditions, pipeline commission, public safety, welding and testing, pipeline material and quality and protection from interference. He stated that the onshore pipeline design code had been selected in accordance with best public safety considerations and is appropriate for the pipeline operating conditions.

He further advised that subject to the developer undertaking to comply with a number of conditions to be laid down in approvals and consents granted, the design is generally in accordance with best international industry practice and that the pipeline is considered to meet public safety requirements. In addition, Mr. Johnson recommended that the pipeline should be laid a minimum of 70 m away from houses and this was included as part of the conditions of the pipeline consent given.

Consent to construct gives the developers the assurance that the pipe can be designed and manufactured to the codes and standards agreed and for the specific route agreed. However, the subsequent installation and commissioning operation for the flow of first gas will be subject to separate approval by the Minister. This will ensure that specific installation operations will be subject to whatever logistical conditions are considered appropriate by the relevant regulatory bodies, in accordance with national and international statutory and other requirements and regulations. The operation of the lines will only be approved — consent for first gas — when the Minister has assurances that the lines, as constructed and installed, are fit for the purpose and have complied with the verification process included in the plan of development approval.

I hope this answers some of the issues raised by the Deputy.