Appropriation Accounts 2023
Vote 13 - Office of Public Works
2:35 pm
Marc Ó Cathasaigh (Waterford, Green Party)
Link to this: Individually | In context | Oireachtas source
The average cost per unit of developing sites, including connectivity to services such as gas, water and communications, and extensive remediation works on the suboptimal sites available, is in the region of €150,000 compared to initial cost. Mr. Conlon is telling me to subtract €150,000 from the figure of €442,000 for the cost of preparing the site.