2022 Report of the Comptroller and Auditor General
Chapter 5: Vote Accounting and Budget Management

9:30 am

Mr. Kevin Meaney:

On average, all of the rest of the projects would take six weeks, but we took about eight weeks with that one. We needed that little bit of extra time where there was a great deal more paperwork but eight weeks was the turnaround time between receiving it and getting it back to the Department of Transport. That would be it.