Mr. Kevin Meaney:
Regarding the metro, there is a technique called “reference class forecasting”. Essentially, it involved benchmarking against other metros that had been built across the world. The exercise removed any unique features of those systems and tried to keep them as close as possible to an Irish-style plan. The model arrived at a central point estimate, which was between €9 billion and €9.5 billion. The range is provided as a probability based on what happened with some metros that were built in other countries. When we speak of €23 billion, we are speaking about the very worst-performing metro systems. However, the average and mean are closer to-----