Public Accounts Committee

2020 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 26 - Education
2018 Report on the Accounts of the Public Services of the Comptroller and Auditor General
Chapter 7 - Purchase of Sites for School Provision
2019 Report on the Accounts of the Public Services of the Comptroller and Auditor General
Chapter 8 - Management of the Schools Estate

9:30 am

Photo of Brian StanleyBrian Stanley (Laois-Offaly, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

We will come back for a second, and possibly a third, round.

There are some questions I myself have on the clerk of works issue at the hearing in October 2020. It is well-established now that the problems that arose in large building projects in the eight or ten years before that arose, were not - the design of the building was not changed - because the architect fell down but because there was no supervision from the employer's representative - in other words, the Department - on site. One of the major problems was simply down to the wall-ties not being dropped on the concrete blocks when the two sets of walls were being constructed. I note now that the Department has committed to, and confirmed that there is, a clerk of works on every large project site and I welcome that. Generally, is the clerk of works an employee of the Department? I want to keep the questions short.