Mr. Hubert Loftus:

The Deputy is correct that the situation is not unique but I would say it is very unusual. The issue there relates to the contractor. I suppose what one has with a contractor, and a tendering, is the contractor committing on a contractual duty to deliver a project to the standard required within a set timeframe and that was not being delivered. That would be the context for the termination there. To follow procurement rules, that requires a re-tendering and that is the issue that has led to the delay in this case.