National Paediatric Hospital Development Board: Financial Statements 2020

9:30 am

Mr. David Gunning:

We need to know the precise delay in order to levy the damages. That is why in practice these liquidated damages are usually assessed at the end of the contract, usually in the final account stages and when things are being concluded between the contractor and the employer.