2020 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 29 - Environment, Climate and Communications
National Broadband Plan Expenditure and Related Matters

9:30 am

Photo of Brian StanleyBrian Stanley (Laois-Offaly, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Mr. Hendrick mentioned a cost of in the region of €2,000 per connection. I refer to the cost of providing the scheme. Adding together the State subsidy and the private finance and dividing that by 540,000 or 550,000 gives a figure of approximately €12,000. Is that correct? I am talking about the actual cost of the scheme. In other words, the average cost for a premise in the orange intervention area to be connected, in the context of the overall scheme, is in the region of €12,000 per premises.