Oireachtas Joint and Select Committees

Wednesday, 23 January 2019

Joint Oireachtas Committee on Health

National Children's Hospital: Discussion (Resumed)

Mr. John Pollock:

The design team will submit additional fees for prolongation. When the project was tendered, the design team won and the first preliminary business case was produced in 2014. It was anticipated that the project would be completed in 2019 but it will not now be completed until 2022 so the design team will submit additional fees for increased scope of work and for having additional people on site to supervise the construction of the project.