Oireachtas Joint and Select Committees

Tuesday, 9 May 2017

Joint Oireachtas Committee on Communications, Climate Action and Environment

Electricity Grid Development Strategy 2017 and Proposed Celtic Interconnector: EirGrid

7:00 pm

Photo of Michael McDowellMichael McDowell (Independent)
Link to this: Individually | In context | Oireachtas source

I welcome the witnesses and I thank them for coming and for the statement they made and the material they have produced. I am interested in the data centres in particular. I am looking at the four scenarios. I notice that in the slow change scenario the total demand for electricity would increase by 28% by 2030 compared to today. In this scenario the only source of demand growth is the connection of new data centres, but the level of investment slows down significantly after 2025.