Ms Maria Graham:
The first phase of metering was for meterable projects, with a target of installing 1 million meters. Of these, 200,000 were not completed but the other households, which were apartment blocks and other properties that were not considered technically feasible, would have been a matter for future phases based on the costs and benefits and an examination of the technology and so forth that would be involved. This would have been a matter for the regulatory process.