Special Report 82 of the Comptroller and Auditor General: Financial Management and Reporting for Fishery Harbour Centres

12:00 pm

Dr. Cecil Beamish:

The steps are to do the sampling and see the results. We are also testing the possibility of alternate ways of dealing with the contamination, because the technology is moving on as are the systems. When there is engineering advice available on both of those elements, and the sampling surveying has been completed and analysed, then a tender specification will be put together. The tender will be advertised and we will analyse the response. The earlier in the year that this can be done, the easier it will be for a contractor to carry out the works in reasonable weather conditions while also taking account of the times that others use the harbour. The objective is to get a new specification for the tender process as early as possible in the new year so that the contract decision can be made as early as possible.