11:55 am

Mr. Dominic Mullaney:

The only one that has started since is the Ballaghaderreen bypass, which started in late 2012 or early 2013. The Ballaghaderreen bypass can be added to the list provided by Mr. O'Mahony, but no major Exchequer-funded project started in 2014. There were advances on the PPP side. In 2013, the Newlands Cross M11 project, from Arklow to Rathnew, proceeded, and this year, the Gort to Tuam section of the N17 and N18 has the go-ahead and has reached financial close.