Public Accounts Committee

Special Report No. 77 of the Comptroller and Auditor General - Dublin Docklands Development Authority: Discussion (Resumed)

11:10 am

Photo of Eoghan MurphyEoghan Murphy (Dublin South East, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The third figure in the Poolbeg site report of 3 October was €350 million, which was based on the price paid for the Readymix site at East Wall. The minutes refer to it at the top of the second page.