Oireachtas Joint and Select Committees

Thursday, 6 December 2012

Public Accounts Committee

2011 Annual Report of the Comptroller and Auditor General and Appropriation Accounts
Chapter 6 - Financial Commitments under Public Private Partnerships
Chapter 16 - Central Government Funding of Local Authorities

11:20 am

Mr. Philip Nugent:

The scheme was announced by the Minister in June. However, it is worth bearing in mind that there are more than 500 applications or cases in the works. An overall timeline from the initiation of the process to the end is involved. In other words, there must be a green light from the lender, the local authority must have deemed the person eligible, the lender must agree that mortgage-to-rent is the appropriate solution, and the borrower must agree to progress down the mortgage-to-rent route. From inception to finalising the transaction we believe the process will take between six and eight months.