Public Accounts Committee

Report of the Comptroller and Auditor General and Appropriation Accounts 2024
Vote 13 - Office of Public Works
Report on the Accounts of the Public Services 2024
Chapter 5 - Development of a Proposed National Science Centre
Chapter 6 - The OPW's Management of Office Accommodation

2:00 am

Mr. John Conlon:

It does, and I fully accept the concerns identified by the Comptroller and Auditor General. There are a number of reasons, including the pandemic which delayed the progression of that contract. Some of the changes within the building took time to resolve. From time to time, you get rent-free zones within which the work was done but the delays were caused by factors that, frankly, were hard to control.