Public Accounts Committee

Report of the Comptroller and Auditor General and Appropriation Accounts 2024
Vote 13 - Office of Public Works
Report on the Accounts of the Public Services 2024
Chapter 5 - Development of a Proposed National Science Centre
Chapter 6 - The OPW's Management of Office Accommodation

2:00 am

Mr. Seamus McCarthy:

Could I add something? As well as reactive maintenance, there could be planned maintenance, which could involve larger jobs such as the replacement of windows. However, there was also a provision in the contract for small-works projects to be carried out. I think there was a limit, possibly of €750,000. We examined this a number of years ago. Some of the projects undertaken were larger capital works projects. There was a further extension with the Brexit projects, some of which were quite substantial and above the initial threshold values expected under the contract.