Current Progress and Future Projections of Uisce Éireann Objectives: Uisce Éireann

Ms Angela Ryan:

At present, that sum is included within the preliminary business case. Obviously, when Cabinet approval is given for that, the amount involved will be out in the public domain. After the next stage of that project will be the final business case. It is important to note that this is not the overall project approval amount. It is the approval of the amount of money to get us through the statutory consenting process, the landowner engagement piece and some of the procurement relating to the project. There is another approval gate, which is known as the final business case, which will be conducted after the current phase.