2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin
9:30 am
Mr. Maurice Buckley:
It is very important to explain that what we are talking about there is a framework contract, which consists of lots of individual projects. Lest anybody listening would misunderstand, it is not that the work cost more than anticipated: it is that more projects were done than anticipated.