Mr. Mark Griffin:

It is effectively a programme to design, build, operate and maintain. It is a gap-funded model. Effectively, the bidder puts in equity and the State puts in a subsidy to meet the gap. That is paid over a 25-year period. The design, build, operation and maintenance are carried out by the company.