Mr. Michael Moriarty:

On the timetable in general, the Comptroller and Auditor General sets out the entire timetable very usefully on page 22. It starts in June 2013. I am sure the Comptroller and Auditor General will agree that we made available to him everything that was in our place. That is every record. We mind everything. That is where the process starts in NAMA's records. I have nothing personal to add in terms of it. Suffice to say that, as far as I am aware, in the course of the examination, everything was made available and there was nothing that was worth documenting on any event before June 2013.