190. To ask the Minister for Education and Skills the current timeline for the commencement and completion of the next stage of works at a school (details supplied) in Castleblayney, County Monaghan; if she will ensure that this project is advanced as a priority; and if she will make a statement on the matter. [9831/24]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The project to which the Deputy refers has been devolved for delivery to Cavan & Monaghan Education and Training Board (CMETB).

The Tender Report has been received by my Department and is currently under review from both a technical and cost perspective. The review is nearing completion and my Department will revert to CMETB directly on the outcome and the next steps to progress this project.

CMETB will be engaging directly with the school authority to keep it informed of progress.

There is an overall pipeline of some 1300 projects across the school system. The current status of all projects is listed on a county by county basis at www.gov.ie. and this is updated on a regular basis to reflect project progress through the various stages of capital appraisal, site acquisition, design, tender and construction.

My Department has a strong track record of delivery of school building projects and this was achieved again in 2023 notwithstanding the wider construction sector environment of high inflation, labour shortages and supply chain issues.

Under Project Ireland 2040, we are investing over €5 billion during the period 2021 to 2025, to add capacity and develop and upgrade school facilities across the country for the almost one million students and over 100,000 staff that learn and work in our schools every day.

My Department is very appreciative of the strong support provided by Government for our education budget. As part of the supplementary budget, €405m additional capital funding was provided in 2023. This helped to alleviate capital funding pressures that arose in 2023 which was reflective of the strong delivery by my Department of school building projects – particularly to support mainstream provision accommodating Ukrainian students and special education needs provision. My Department’s overall capital out-turn for 2023 was €1.264 billion.

We continue to have a strong pipeline of projects for delivery under the school building programme involving circa. 300 projects currently at construction, which include 34 new school buildings. We also have a large modular accommodation programme delivering urgently needed school places. The Department has always operated a tightly prioritised approach to the school building programme, focused over recent years on the delivery of additional capacity where required, and this will continue to be the case.

Photo of Gerald NashGerald Nash (Louth, Labour)
Link to this: Individually | In context | Oireachtas source

191. To ask the Minister for Education and Skills when the construction contract for the new building for a school (details supplied) in County Louth on a site at Cement Road, Drogheda will go out to tender; if she will provide a timeline for the completion of the project; and if she will make a statement on the matter. [9839/24]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The joint Major Building Project for St Ita's & St Mary's Special Schools, Drogheda, is currently at an advanced stage of architectural planning -Stage 2(b) – Detailed Design, where the design team secure all Statutory Applications and prepare the suite of tender documents.

The Design Team have recently secured Planning Permission and Disability Access Certification, and a decision from the Local Authority is pending regarding Fire Safety Certification.

The design team are completing work on the Stage 2(b) submission, to be forwarded to my Department for review.

Upon receipt, review and approval of the Stage 2(b) submission, the Department will inform the School Authorities and their Design Team of the progression of the major project to the next stage of Architectural Planning – Tender Award.