Flood Relief Schemes
Thomas Gould (Cork North Central, Sinn Fein)
Link to this: Individually | In context | Oireachtas source
31. To ask the Minister for Public Expenditure and Reform the current status of works on the weir at Ballincollig Regional Park; and if he will make a statement on the matter. [4454/24]
Patrick O'Donovan (Limerick County, Fine Gael)
Link to this: Individually | In context | Oireachtas source
Ballincollig Weir, which is part of Ballincollig Regional Park, is in the ownership of Cork City Council since the boundary change between Cork County and City in June 2019. The Weir had apparently been in disrepair for many years before a breach occurred in December 2014, which has left the weir in extremely poor condition.
While there are no hydraulic benefits to the flood relief scheme from the weir, the Lower Lee Flood Relief Scheme Steering Group in 2021, committed to the incorporation of remedial works to the weir as part of the construction contract and budget for the Scheme, if appropriate.
The nature of any such remedial works will be subject to an assessment of planning, structural, fisheries and cultural heritage considerations, which the Lower Lee Flood Relief Scheme Steering Group has asked the Scheme’s design consultants, contracted by the OPW, to review. The consultants’ proposal to undertake a preliminary feasibility assessment and constraints study for the reinstatement of Ballincollig Weir has been approved and is ongoing. Site surveys and inspections have now been completed, and a report is being prepared.