Written answers

Tuesday, 14 November 2023

Department of Public Expenditure and Reform

Office of Public Works

Photo of Paul DonnellyPaul Donnelly (Dublin West, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

156. To ask the Minister for Public Expenditure and Reform the Garda stations within the DMR that are scheduled for refurbishment by the OPW between now and the first half of 2024; the nature of the refurbishment, per station, in tabular form; and if known, when refurbishment works will commence. [49861/23]

Photo of Patrick O'DonovanPatrick O'Donovan (Limerick County, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I can confirm that the Office of Public Works has scheduled refurbishment works to Garda Stations within the DMR to be carried out between now and the first half of 2024.

The Garda Stations and the nature of the works to be carried out are outlined in the table below and include only works valued in excess of €150,000. The works outlined relate to works funded both by OPW and An Garda Siochána.

The Commencement dates for the scheduled works are subject to the final sign off of operational and design requirements by An Garda Síochána and where necessary, successful tendering process.

Garda Station Nature of the works Works Due for Commencement
Cabra GS Refurbishment/ reconfiguration of portacabins to rear. Q2 2024
Lusk GS Reconfiguration and upgrade of station, including conversion of married quarters Q2 2024
Swords GS Reconfiguration of 2 rooms at first floor level to provide new canteen and kitchen area On site, to complete end 2023/ early 2024
Finglas GS Investigation and repair of pre tensioned glass façade to tower On site, to complete end 2023/ early 2024
Malahide GS Maintenance works to attics and large scale roof repair to valleys. On site, to complete end 2023/ early 2024
Malahide GS Refurbishment of cast iron railings, painting / refurbishment of façade and windows Q2 2024
Raheny GS Structural repair works to 2 storey block, including underpinning, works to brickwork façade, and new footpath. Q3 2024
Crumlin GS Prisoner Processing Area Spec Upgrade Q2 2024
Sundrive Rd GS Public Office Refurbishment Q2 2024
Greystones GS Boundary Wall repairs and car park resurfacing Q1 2024