Written answers

Tuesday, 3 October 2023

Department of Education and Skills

Special Educational Needs

Photo of Cian O'CallaghanCian O'Callaghan (Dublin Bay North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

326. To ask the Minister for Education and Skills further to Parliamentary Question No. 693 of 11 September 2023, the measures that her Department is taking to address further delays experienced by an autism unit in a school (details supplied); if her Department will take action to ensure that necessary work commences as soon as possible; the reason that further delays have taken place, meaning the new opening date will be sometime in November 2023; and if she will make a statement on the matter. [42668/23]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

As the Deputy is aware, the project is being delivered under the Department’s Devolved SEN Reconfiguration and Modular Accommodation programme. This programme provides project management supports to enable the accommodation to be provided as quickly as possible and helps to ease the administrative workload for individual schools in relation to the management and delivery of the project.

The overall construction sector environment is challenging. The Department is working closely with the Project Management team and the particular school's Design Team to ensure the project is completed as quickly as possible the date remains at November 2023 for completion however, work is ongoing to try to improve this timeline.