Written answers
Wednesday, 20 September 2023
Department of Transport, Tourism and Sport
Rail Network
Eoin Ó Broin (Dublin Mid West, Sinn Fein)
Link to this: Individually | In context | Oireachtas source
87. To ask the Minister for Transport, Tourism and Sport to explain the long delay in the completion and opening of the Kishogue train station in Clonburris, County Dublin; and to provide a date for when the station will be completed and open. [39826/23]
Eamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source
As Minister for Transport, I have responsibility for policy and overall funding in relation to public transport. The National Transport Authority (NTA) has statutory responsibility for the planning and development of public transport infrastructure in the Greater Dublin Area including, in consultation with Iarnród Éireann, the development and implementation of rail infrastructure. In this context, Kishoge railway station is due to open next year.
Noting the NTA's responsibility in the matter, I have referred the Deputy's question to the NTA for a more detailed reply. Please contact my private office if you do not receive a reply within 10 days.
Eoin Ó Broin (Dublin Mid West, Sinn Fein)
Link to this: Individually | In context | Oireachtas source
88. To ask the Minister for Transport, Tourism and Sport to provide an update on the electrification of the train line to Hazelhatch through Clondalkin, Kishogue and Adamstown; and to provide a date for the completion of these works and a date for the commencement of the Dart service on this enhanced line. [39827/23]
Eamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source
As Minister for Transport, I have responsibility for policy and overall funding in relation to public transport. The National Transport Authority (NTA) has statutory responsibility for the planning and development of public transport infrastructure in the Greater Dublin Area, including planning and implementation of the DART+ Programme.
Noting the NTA's responsibility in the matter, I have referred the Deputy's question to the NTA for a more detailed reply in relation to specific issues raised. Please contact my private office if you do not receive a reply within 10 days.