161. To ask the Minister for Education and Skills the status of schools building projects (details supplied) based on time to proceed to construction, type of accommodation to be provided and the projected budget allocation, in tabular form; and if he will make a statement on the matter. [9165/17]
Richard Bruton (Dublin Bay North, Fine Gael)
Link to this: Individually | In context | Oireachtas source
I wish to advise the Deputy that the current status of the building projects to which he refers in the details supplied are outlined in the following table.
I also wish to advise the Deputy that until such time as planning permission has been secured, or the building projects have progressed to and completed tender stage and the appointment of a building contractor, it will not be possible to provide an indicative timeframe or cost for the completion of the construction of these projects.
While the first two projects listed on the table are under construction and are being delivered under the Public Private Partnership (PPP) process, my Department does not give a value for schools delivered under the PPP process, as they are part of a bundle and the capital cost of individual schools is considered commercially sensitive and not disclosed.
County | Roll Number | School Name & Address | School Type | Year project will proceed to construction | Status | Type of Accommodation |
---|---|---|---|---|---|---|
Wicklow | 07246U 70821M | Scoil Philomena, Bray Coláiste Raithin, Bray | Primary Post Primary | 2016 | Schools will be co-located on same site. Currently under construction, new schools to be completed in Q4 of 2017. | New schools |
Wicklow | 20045K | Gaelscoil Chill Mhantáin, An Casadh Meidhreach, Rath Naoi | Primary | 2016 | Stage 2B * | New school |
Wicklow | 20346B | Kilcoole Primary School, Kilcoole | Primary | 2016 | Stage 2B * | Extension |
Wicklow | 61830M | St. David's Holy Faith, Co-Educational School, Greystones | Post Primary | 2016 | Stage 2B * | Extension & refurbishment |
Wicklow | 20278K | Newtownmountkennedy Primary School, Kilcoole | Primary | 2018 | Stage 2A – Developed Design. | New school and Special Needs Unit |
Wicklow | 20473I | Greystones Community NS, Greystones | Primary | 2018 | Site currently being acquired. Architectural Planning can commence when site has been acquired. | New school and Special Needs Unit |
Wicklow | 70760S | Blessington Community College | Post Primary | 2018 | Architectural Planning has commenced. | Extension |
Wicklow | 70790E | Coláiste Bhríde, Carnew | Post Primary | 2018 | Architectural Planning has commenced. | Extension |
Wicklow | 70800E | St Kevin's Community College, Dunlavin | Post Primary | 2018 | Architectural Planning has commenced. | Extension |
Wicklow | 76076M | Coláiste Chraoibh Abhainn, Kilcoole | Post Primary | 2018 | Architectural Planning has commenced. | Extension |
Wicklow | 76106S | Gaelcholáiste na Mara, Arklow | Post Primary | 2018 | Architectural Planning has commenced. | New school |
Wicklow | N/A | KWETB Bray | Post Primary | 2018 | Architectural Planning has commenced. | Extension |
Wicklow | 20243O | GS na Lochanna | Primary | 2019-2021 | Suitable site to be acquired. | New school |
Wicklow | 61770U | Arklow CBS | Post Primary | 2019-2021 | Architectural Planning has commenced. | Extension |
Wicklow | 61820J | Loreto Secondary School, Bray | Post Primary | 2019-2021 | Architectural Planning has commenced. | Extension |
Wicklow | 70810H | Avondale Community College, Rathdrum | Post Primary | 2019-2021 | Architectural Planning has commenced | Extension |