Department of Public Expenditure and Reform

Roads Maintenance

Photo of Patrick NultyPatrick Nulty (Dublin West, Independent)
Link to this: Individually | In context | Oireachtas source

101. To ask the Minister for Public Expenditure and Reform if he will provide in tabular form the contract price, extras claimed, extras money agreed and total cost in respect of the recent rebuilding of the main road in the Phoenix Park, Dublin; and if he will make a statement on the matter. [49770/13]

Photo of Brian HayesBrian Hayes (Dublin South West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Contract price including further length of road added due to deterioration in stability and safety at contract rates: €1,990,902.94

Additional costs due to unanticipated archaeology and unforeseen ground conditions necessitating extra excavations, filling etc: €643,763.21

Total Cost: €2,634,666.15