Department of Transport
Rail Network
10:00 pm
Áine Brady (Kildare North, Fianna Fail)
Link to this: Individually | In context
Question 296: To ask the Minister for Transport the plans his Department has to upgrade the Maynooth rail line; the timescale for such plans; and if he will make a statement on the matter. [42402/08]
Noel Dempsey (Meath West, Fianna Fail)
Link to this: Individually | In context
The detailed planning and design of the upgrade works on the Maynooth line is a matter for Iarnród Ãireann. I understand that Iarnród Ãireann intend to undertake the resignalling and the removal of level crossings on the line in the period 2009-2012 and that the electrification of the line will progress in tandem with the resignalling. These projects will provide for a significant increase in trains per hour from 7 currently to 17 trains per hour. When completed the Maynooth line will become an integral part of the DART network.
Áine Brady (Kildare North, Fianna Fail)
Link to this: Individually | In context
Question 297: To ask the Minister for Transport the amount of State funding allocated to the Kildare route project; the progress of the project to date; and if he will make a statement on the matter. [42403/08]
Noel Dempsey (Meath West, Fianna Fail)
Link to this: Individually | In context
Exchequer funding of â¬269m has been approved for the Kildare Route Project and â¬157,978,144 has been paid to date. The construction phase of the Kildare Route Project commenced in June 2007 and is due to be completed by early 2010.