Question 296: To ask the Minister for Transport the plans his Department has to upgrade the Maynooth rail line; the timescale for such plans; and if he will make a statement on the matter. [42402/08]

Photo of Noel DempseyNoel Dempsey (Meath West, Fianna Fail)
Link to this: Individually | In context

The detailed planning and design of the upgrade works on the Maynooth line is a matter for Iarnród Éireann. I understand that Iarnród Éireann intend to undertake the resignalling and the removal of level crossings on the line in the period 2009-2012 and that the electrification of the line will progress in tandem with the resignalling. These projects will provide for a significant increase in trains per hour from 7 currently to 17 trains per hour. When completed the Maynooth line will become an integral part of the DART network.

Photo of Áine BradyÁine Brady (Kildare North, Fianna Fail)
Link to this: Individually | In context

Question 297: To ask the Minister for Transport the amount of State funding allocated to the Kildare route project; the progress of the project to date; and if he will make a statement on the matter. [42403/08]

Photo of Noel DempseyNoel Dempsey (Meath West, Fianna Fail)
Link to this: Individually | In context

Exchequer funding of €269m has been approved for the Kildare Route Project and €157,978,144 has been paid to date. The construction phase of the Kildare Route Project commenced in June 2007 and is due to be completed by early 2010.