Question 412: To ask the Minister for Education and Science when her Department will sanction the building for a new school (details supplied) in County Mayo; and if she will make a statement on the matter. [29361/07]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

An application for capital funding towards the provision of new school building has been received from the school authority referred to by the Deputy. An assessment of projected enrolment trends, demographic trends and housing developments in the area will be required in order to determine the long term projected staffing figure on which the school's accommodation needs will be based. Once the long term projection has been determined and agreed with the school authorities the required building project will be considered in the context of the multi-annual School Building and Modernisation programme.

Photo of John O'MahonyJohn O'Mahony (Mayo, Fine Gael)
Link to this: Individually | In context

Question 413: To ask the Minister for Education and Science further to Parliamentary Question No. 379 of 9 October 2007, when the building budget for the small schools scheme will be announced for 2008; if a school (details supplied) in County Mayo will be included; and if she will make a statement on the matter. [29362/07]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

The breakdown of the 2008 building budget between the devolved and other schemes has not yet been determined.

Photo of Jan O'SullivanJan O'Sullivan (Limerick East, Labour)
Link to this: Individually | In context

Question 414: To ask the Minister for Education and Science if her Department has given permission to go to tender in relation to a school (details supplied) in County Limerick; if not, if she will expedite the matter in view of the fact that the children currently have to use outside toilets, that the site is ready and that planning permission has been secured; and if she will make a statement on the matter. [29364/07]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

Approval of the Stage 3 (developed sketch scheme) was issued to the Board of Management of the school in a letter dated 14 November 2007. In addition, preparation of Stage 4/5 tender documents has commenced. It is not possible to say at this point when construction will start. However, my Department will be in contact with the school authorities about further progress as soon as the tender documents have been completed.