Photo of Josepha MadiganJosepha Madigan (Dublin Rathdown, Fine Gael) | Oireachtas source

I congratulate Senator Dooley on his appointment to the Seanad and thank him for raising this matter. It allows me to clarify the current position on Gaelscoil Mhíchíl Cíosóg which, as the Senator said, is a Catholic co-educational school with an emphasis on the Irish language. I understand it has 471 pupils; the Senator said there are 481. Either way, it has a large school population.

I will outline some of the background to this matter. In 2014, the school authority applied to my Department for capital funding under the additional school accommodation scheme. The Department subsequently approved an extension to the existing school building comprising five mainstream classrooms and two special education tuition rooms, on which I commend the school. Delivery of the project was devolved to Limerick and Clare Education and Training Board.

At that time, the school authority was requested to manage its enrolment and not grow beyond the principal and 18 mainstream teachers in line with the approved accommodation. Following the appointment of the design team to the project in 2015, a master plan for the project was submitted to the Department for consideration. It outlined accommodation for a principal and 20 teachers and included a substantial new physical education, PE, and general purpose area, along with ancillary and administrative areas which were not approved as part of the project brief and would not qualify for funding under the terms of the additional school accommodation scheme.

At a meeting with officials from the Department that year, the school authority signalled its intention to reject the devolved funding offer. However, in 2018 a further meeting between officials and the school authority was held and agreement was reached to increase the scope of the project to include two additional mainstream classrooms, in effect raising the long-term projected staffing for the school to one principal and 20 teachers. At that meeting, the matter of a new PE and general purpose area, to which the Senator referred, was also discussed.

My officials once again informed the school authority that the provision of a PE hall did not form part of the additional school accommodation scheme and could not be considered for inclusion in the accommodation brief for the proposed extension. The school authority was advised at that meeting that it was open to it to apply for this accommodation under the major capital programme to be considered in future years. The approved building project is, as the Senator knows, currently in the early stage of the architectural design process.

A stage 1 submission was approved by the Department in April 2020. The school authority had again requested that the brief be amended to include a sports hall and had submitted drawings showing a sports hall included. The position of the Department, from my instructions, remains unchanged and it is not possible to fund a PE hall or general purpose room under the additional school accommodation scheme.

As the Senator will be aware, capital planning and budgeting are undertaken on a multi-annual basis. Under Project Ireland 2040, the education sector will receive approximately €12 billion between 2018 and 2027. This includes €8.8 billion for the school sector and €2.2 billion for higher education infrastructure. The specific allocations in each area are closely monitored and may be adjusted from year to year to take account of project progress and other factors. Since 2018, in excess of €1.2 billion has been invested in capital infrastructure under the school building programme. A further €725 million has been allocated for investment in 2020.

As the Senator knows, the Department has a large pipeline of projects for delivery under the school building programme. The main elements of the pipeline currently include 372 large-scale projects and approximately 800 projects for delivery under the Department's additional school accommodation scheme, which includes the additional accommodation project for Gaelscoil Mhíchíl Cíosóg.