Schools Building Projects Status

10:30 am

Photo of Jim DalyJim Daly (Cork South West, Fine Gael) | Oireachtas source

The information I have been given by the Minister indicates it takes up to 12 weeks for the pre-qualification stage and seven to eight months for tender. I cannot give a definitive timeframe because one must always consider events, dear boy, events. I am very familiar with such projects. Clonakilty Community College is on my doorstep and is slightly ahead of the project in Ennistymon as the tender is about to be opened. It has been through the stages that the Ennistymon project must undergo and in that case the two stages took two or three months more than the estimated 12 month period. This project may be lucky but, realistically, construction will begin in 12 to 15 months based on the information I have been given, subject to the caveat that unforeseen events may arise.